Six large-scale solar projects at risk of being canceled

Six large-scale solar projects at risk of being canceled

At least six of 11 projects solar energy belonging to the first tranche (“tranche”) of acquisition by the Electric Power Authority (AEE) run the risk of being canceled if, at the end of the month, the interconnection agreement that each of the private proponents must sign with LUMA Energy to make way for construction.

Of the nine contracts whose date to comply with all the stipulated “subsequent conditions” expired on September 30, only the project of Convergent Coamo –with a capacity of 100 megawatts (MW)– managed to finalize both the interconnection agreement with LUMA Energy and the rest of the requirements prior to the execution of the work, he specified. Jaime Umpierrehead of Operations at PREPA.

“There are two other projects that signed the interconnection agreements, but have not complied with all the requirements, the subsequent conditions within the PPOA (power purchase agreement)”said Umpierre, referring to the Solaner Puerto Rico and Go Green USA projects, which are expected to have capacity for 40 MW and 100 MW, respectively.

Six other projects faced the September 30 deadline, but currently have pending compliance with certain requirements and have not signed the interconnection agreement either: Tetris Power (45 MW), Pattern Barceloneta Solar (70 MW), CS-UR Juncos PV (125 MW), Yabucoa Solar (32.1 MW), Guayama Solar Energy (50 MW) and Ciro Two Salinas (68 MW).

Umpierre assured, however, that the contracts remain valid and none of the projects have been canceled.

“(For) all of these projects, which are nine in total, the construction clock began ticking on October 1, which is the 24-month period established in the PPOA”, explained the official, in reference to the term established for each of the projects to begin injecting energy into the network. In light of that deadline, the projects must be operational by October 2025.

Of the nine contracts whose date to comply with all the stipulated “subsequent conditions” expired on September 30, only the Convergent Coamo project – with a capacity of 100 megawatts (MW) – managed to finalize both the interconnection agreement with LUMA Energy and the rest of the requirements prior to the execution of the work, said Jaime Umpierre, head of Operations at PREPA. (The Associated Press)

Despite the current exemption from compliance with the different conditions, the engineer clarified that PREPA granted LUMA Energy and the proponents until October 31 to finalize the interconnection agreements and other requirements.

Earlier this year, as proponents and PREPA renegotiated the terms of PPOAs signed in 2022, the Puerto Rico Energy Bureau It provided that private developers would not assume the increases to the original costs that the interconnections would entail. After several “policy changes”, LUMA Energy decided that it would take charge of executing the interconnection works through an external contractor. The interconnections, in summary, serve to bring the energy generated by the solar projects to the transmission lines operated by the consortium.

“The waiver was granted to allow reasonable time for them to comply with certain conditions of the contract, but the construction clock began to run. (…) We urge you to sign, because you have already signed three (interconnection agreements). LUMA and PREPA are open for this to be signed. “We are giving October 31 for them to sign and we are not going to give additional extensions.”Umpierre stressed.

The Chief of Operations attributed the delays to “concerns” of the Association of Renewable Energy Producers “in relation to terms that they understand are conflicting with the terms of the PPOA, the risk represented by the time it takes for the LUMA contractor to build the interconnection… I do not see that they are problems that will not have a solution within three weeks.” . “There is not going to be an increase to the developer, that is not a controversy.”

At the time of this publication, LUMA Energy had not responded to a request for reaction from The new day.

Earlier this year, while the proponents and PREPA renegotiated the terms of the PPOAs signed in 2022, the Puerto Rico Energy Bureau ruled that private developers would not assume the increases to the original costs that the interconnections would entail.
Earlier this year, while the proponents and PREPA renegotiated the terms of the PPOAs signed in 2022, the Puerto Rico Energy Bureau ruled that private developers would not assume the increases to the original costs that the interconnections would entail. (Shutterstock)

Two other solar projects of “tranche” 1, in the hands of Clean Flexible Energy – a subsidiary of AES–, face a closing date of November 30, while a handful of energy storage battery projects wait for authorization from the Fiscal Oversight Boardsaid Umpierre.

An issue to correct

For the consumer representative in the PREPA Governing Board, Tomas Torres Placaregarding the other sections of clean energy acquisition, “one of the important lessons we can learn is that How the issue of interconnection costs is dealt with must be significantly improved.. “We already saw that last month these costs were not taken into account.”

“For many of these contracts, their cost was affected and now, that the contracts are signed, the costs are higher than established. That is not acceptable. There must be greater control and supervision over the actions of this operator (LUMA), beyond what the company is currently doing. Authority for Public Private Partnerships“, said Torres Placa.

For the customer representative, the increases have an impact on the rate that consumers pay, since the fixed expenses of the electrical system – the transmission and distribution network – represent a cost of around 8 cents per kilowatt hour (kWh). Therefore, any PPOA that includes a cost in excess of 12 cents per kWh results in a rate greater than 20 cents, the goal established in public policy.

Of the 11 contracts approved in tranche 1, six include an energy purchase cost greater than 12 cents.