More than a year since the demolition of the wall erected in front of the Sol y Playa condominium was ordered, starting Monday work will begin to return the affected area on Los Almendros beach, in Rincon, to its natural state.
According to the Department of Natural and Environmental Resources (DRNA), It is expected that the work will begin with the mobilization of the necessary machinery to the place where a recreational facility for the housing complex was being illegally built.
On Tuesday, demolition work is specifically projected to begin, from 6:00 am to 6:00 pm, the agency confirmed.
The Board of Owners of the Sol y Playa condominium had reported, through a motion presented before the Court of First Instance of Aguadilla, that the work, carried out by the company West Development and Heavy Rental, would begin “on or around” this Monday.
The motion indicated that coordination with the DRNA was necessary to demarcate the area and assign security guards, in accordance with conversations held by the parties. The agency informed The new day that, in effect, There will be personnel from the Vigilante Corps assigned while the work is carried out.
The work not only involves the demolition of the recreational areas, but also the restoration of the land to its original state. Although there are various factors that affect the amount of time it may take, the works could last for 90 days.
Initially, the work was scheduled to begin on October 2, however the contractor faced problems obtaining the performance bond required by the DRNA, which could fluctuate between $9,000 and $10,000.
On February 14, the Court of First Instance ordered the Council of Owners of the Sol y Playa condominium to demolish the structure, remove debris and return the affected area to its natural state. To do this, it gave, as a deadline, March 1, 2023, a date that was not met.
The construction of the recreational facilities, which were devastated by Hurricane Maria in 2017, were the focus of protests carried out by environmental groups and citizens in defense of the beaches, during the summer of 2021. The place was also the scene of clashes between police and activists. The protests intensified when a hawksbill turtle became stranded in the building while laying its eggs.
The works were paralyzed by the Planning Board, an entity that sued the condominium owners in August 2021.