Naranjito – The Highway and Transportation Authority (ACT) showed this Thursday the execution of some of the main stages regarding the repair work of the emblematic Naranjito cable-stayed bridge: the placement of the filler – a polymeric material – on the surface of the structure, which when it covers the two lanes currently being worked on will have eliminated the undulations that represented a construction and safety problem since its inauguration.
“An extremely meticulous job is being done, it is almost a craftsmanship, because what we want is not only to eliminate the undulations that were there in the beginning, but also for the water to drain in the future, since we do not want it to stagnate in the the bridge, but go towards the drains”said the executive director of the ACT, Edwin Gonzalez Montalvowhen describing the complexity of the work in progress.
In an aside with The new dayindicated that the ACT and the main contractor of the work –Ferrovial Construction– are already working in meetings with the company Freyssinet, which will be in charge of the maintenance work on the bridge stays.
“It is a world-class company, a specialist in these stays, to ensure that proper maintenance will be given to these stays, the boots, the wetsuits at the end and that the bridge is completely in good condition to be traveled by citizens. ”said Gonzalez Montalvo.
Freyssinet is scheduled to begin work on the stays in late October or early November.
“They will be verifying that (the stay system) does not have any water infiltration… that, if they have any coating that needs to be changed, it will be changed. “It’s a maintenance job on all those stays to make sure they last for years to come,” he described.
The bridge was closed on January 30 to begin repair work., which affected thousands of residents in Naranjito, Barranquitas, Comerio, Morovis and Toa Alta, who frequently pass through the structure. Two and a half months later, The ACT opened, on April 18, a reversible laneafter studies concluded that it was viable, while the arrangements continued, to serve vehicular traffic during the morning and afternoon peak hours.
The studies, in turn, are part of a forensic analysis that the ACT carries out and that, according to the public corporation itself, seeks to assign responsibilities regarding the irregularities and construction defects revealed in a journalistic investigation of this newspaper.
“I can’t comment on that, because that is part of the investigation, but basically we identified the problem and our solution is with data,” said the engineer. Luis Velezproject manager, when questioned about the causes behind the problems on the bridge.
Regarding the work to level the surface of the slab, Velez explained that “the bridge had some undulations, it had some lower points and others higher. We eliminate the highest points, we begin to create some profiles, we survey and create both a longitudinal and transverse profile, and that creates the fills. Some (spaces) are thin, others are thicker, and others will be much thicker.”
In August, a monthly report prepared by Ferrovial Construction concluded that the work has a delay of 124 calendar days, which would place the completion of the work in November 2024. But the director of the ACT reiterated this Thursday that The completion date of the project, with its four lanes corrected and ready for use, will be in the summer of 2024. He assured that he is not under any pressure to reopen the bridge in its entirety before the general elections in November 2024.
As The new day had published, the objective of the ACT continues to be to open two of the bridge’s lanes to the public next December, one in each direction, and then move to correct the undulations and carry out the corresponding work on the remaining two lanes.
“No, at no time has anyone put any pressure on me. “When the lanes opened, it was with data, unlike, perhaps, in the past”, Gonzalez Montalvo emphasized.
The official visited the bridge this Thursday in the company of the mayor of Naranjito, Orlando Ortiz Chevreswho indicated that the initial closure of the bridge was reflected in a decrease in the collection of the Sales and Use Tax (IVU), so its reopening is key.
“Seeing that this problem will now be resolved fills us with pride, because this is a door. This is the mountain gate. “This is not just any bridge, it is an architectural icon and the fact that we are close to reopening it will undoubtedly be important for the economic development and quality of life of this region.”, the mayor stated.