It is the headache of thousands of residents in the western region and has even been the subject of research for engineering students from the Mayaguez University Campus (RUM). He heavy vehicular traffic which is concentrated in a 1.4 mile stretch, with its worst point at the intersection in front of the College entrance, makes daily routines difficult, but that could change in the coming years.
With a investment of $185 million and a ready design, the Highway and Transportation Authority (ACT) is preparing to begin a qualification process that will culminate with the selection of a construction firm that will be in charge of the road transformation of the section through which, on average, 33,500 vehicles pass daily.
“Mayaguez It is a regional city, and this project is one of regional impact. “We are moving to elevated roads and roundabouts to turn that segment in front of the School into an expressway.”, indicated the executive director of the ACT, Edwin Gonzalez Montalvoin an interview with The new day.
Specifically, improvements will be made at the intersections of the PR-2 highway with the PR-102, the PR-2 with the PR-3108 (Chardon street), the PR-2 with the PR-239 and the PR-2 with the Luis Llorens Torres street. In addition, the renovation of the area will include bicycle lanes and pedestrian crossings.
For the engineer Gonzalez Montalvo, born in Mayaguez and raised in Mocha, this project has a particular importance and relevance. “I studied my high school and master’s degree at the College of Mayaguez, and many times, in civil engineering classes, this is the typical project: how to solve the problem of Mayaguez at the intersection in front of the College. When I got here, to the Highway Authority, I asked what was being done with that intersection,” he said.
In May 2022, the ACT submitted a proposal to the programs known as MEGA, INFRA and RURAL, through the Discretionary Grant for Multimodal Projects (MPDG, in English) of the Federal Department of Transportation (DOT, in English), a competitive procedure in which other state governments in the United States also submit applications.
In September of last year, the DOT approved $90 million, through INFRA, for the construction of the project that the ACT named “La Vita.” This is the first time that the public corporation has won a subsidy of this type, through competition.
“We competed head-to-head with several states, and we were one of 26 projects that won funding. On September 28, 2022, they gave us the news that we had won $90 million for Puerto Rico”, Gonzalez Montalvo highlighted.
To contribute to the total investment required by the work, the governor Pedro Pierluisi announced the signing of an agreement between the Housing Department and the ACT allocating $49 million in recovery funds for improvements to PR-2. The money will come from the CDBG-Mitigation (CDBG-MIT) program, which provides funds to increase resilience to future disasters. The remaining amount – $46 million – will be covered with state funds.
“This project, in Mayaguez, is critical for the western area, since it has an impact on over 365,000 residents, merchants and visitors, and provides access to the main commercial, industrial, residential, hotel, hospital and educational points of the Sultana del Oestse,” the governor stressed in writing.
:format(jpeg)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/N23XSIIDHBERLBOF2YZDISWDEE.jpg)
What do the improvements consist of?
The improvements described by the ACT include eliminating several signalized intersections and vehicular movements or maneuvers, reducing travel time and improving corridor safety. The main purpose of the project is to alleviate traffic congestion on the stretch.
For example, At the intersection of PR-2 and PR-102, the traffic light will be eliminated, and traffic will continue via express. To change lane direction, the user must proceed to the next intersection under the bridge, towards what is known as a Texas U-turn.
In the PR-2 with PR-3108 (Chardon street) –a connector to the Miradero neighborhood, several RUM buildings and the closed zoo–, instead of having to stop at just one, the driver will exit the traffic and go under a bridge to continue its normal flow. “If someone was going towards Mayaguez or towards the College, they would take some elevated roads and follow the express route towards the Mayaguez School”explained Gonzalez Montalvo.
The design also includes eliminating the intersection of the PR-2 with PR-239 (Mayaguez Terrace)which will be replaced with a Texas U-turn type turn.
Refering to PR-2 with Luis Llorens Torres streetthe intersection in front of the RUM, two mega roundabouts will be built. “All that traffic from the School is going to travel through these two mega roundabouts”indicated the executive director.
On one of the roundabouts, there will be two elevated roads – with two lanes each – heading towards Ponce and Aguadilla. “A ramp, a ‘flyover’, is being carried out to remove all the traffic that comes from the PR-2 branch, and citizens can take that ramp and travel towards Aguadilla or Ponce,” he described.
:format(jpeg)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/YIKQJIIA65BBLIW2RJK66VGMNA.jpg)
There will be an educational phase
To verify the effectiveness of the design, the ACT carried out modeling using computer programs that allow analyzing how traffic would function under different scenarios, until reaching the final design that won the allocation of funds.
The engineer Lissette Lugoassistant director of Infrastructure of the ACT, announced that there will be an educational phase aimed, particularly, at the residents of the area, in which a traffic simulator with the new design will be used, which will be created at the RUM, as occurred with the intersection of divergent diamond, in Gurabo.
“It is something totally innovative, something that has not been seen in Puerto Rico. It is a combination of two roundabouts, so it is a very comprehensive project, and I know that it will be the solution for what the situation is there in the area,” said Lugo.
In addition, when submitting the proposal, the project also included environmental, noise and archaeological impact studies.
The ACT hopes to publish this month the request for qualifications to firms interested in competing to complete the project. Once it is determined which companies are qualified, it will publish a request for proposals. Construction is scheduled to begin no later than October 2024 and would last between three and four years.
The ACT also evaluates the impact that the construction works will have on traffic in the area and what the alternative routes will be.
“It is an extremely congested corridor, and We are seeking that, while we have construction, the daily life of citizens is impacted as little as possible. because, if there is a plug, there does not have to be any more plug,” Gonzalez Montalvo stressed.