The Luis A. Ferre highway (PR-52) will be the scene, until 2026, of a series of reconstruction works on the pavement, in the lanes in the direction of San Juan to Caguas, but Governor Pedro Pierluisi stated this Tuesday that Measures have been taken to minimize traffic congestion, including free use of the dynamic lane on weekends.
The work, which began on November 8, will be carried out during limited hours to avoid traffic jams, the president said. The work schedules will be as follows: Wednesday and Thursday, from 5:00 am to 2:00 pm, while, from Friday to Monday, they will take place between 9:00 pm and 5:00 amhe said during a press conference.
“This will take until 2026 to be completed, because it is being done in such a way that it does not significantly affect traffic on the roads,” said Pierluisi.
The reversible dynamic lane will be available for free on weekends in the direction of Caguas, it was reported.
The tasks, which cost $22 million in federal and state funds, involve cutting and removing slabs, depositing concrete, curing slabs, marking pavement, installing cat eyes and other safety devices.
Questioned about why Metropistas, which recently obtained a public-private partnership (PPP) contract to manage the road, was not responsible for these improvements, the governor and the executive director of the Highways and Transportation Authority (ACT), Edwin Gonzalezargued that these are works that were already scheduled and that were presented to the private entity before the contractual agreement was consummated.
In October, the governor announced that the company Abertisparent company of Metropistas, will be in charge, through a 30-year PPP, of the operation, financing, improvements and maintenance of the toll highways PR-20 (Rafael Martinez Nadal), PR-52 (Luis A. Ferre), PR -53 (Jose Celso Barbosa) and PR-66 (Roberto Sanchez Vilella).
“Part of the PPP agreement is that all ongoing projects using federal funds and in the hands of the ACT will remain in the hands of the ACT until they are completed. The investment commitment that the new public-private entity has is for funds that this entity is going to be contributing to this highway, apart from the funds that we have already processed with the federal government,” Pierluisi stressed.
He added that the “financial closing” to finalize the APP must occur in December.
From elsewhere, Gonzalez anticipated that the contract to expand the PR-5 highway will take place soon., which currently runs between Catano and Bayamon. This is a project that involves an investment of more than $240 million and will extend from the Bayamon soccer field to the cable-stayed bridge in Naranjito.
On the cable-stayed bridge, the head of the ACT reiterated that the four lanes will be open in both directions next summer.