Between 40,000 and 55,000 clients in Carolina, Canovanas and Rio Grande will face electrical service interruptions this Sunday, the day in which LUMA Energy will be replacing a series of switches at the Sabana Llana substation, located in the first of the three municipalities.
According to LUMA Energy’s announcement, The repair work will impact the energy supply for 14 hours, between 1:00 am and 3:00 pm
In a press conference this Thursday, the president of the company, Juan Sacaand operating officials of the consortium, insisted that the works – which are part of federal projects aimed at improving electrical substations – will have a substantial effect on the quality of long-term service in towns as distant as Manati and Humacao, that cover more than half of the country’s consumers.
“LUMA will provide the specific information on the sectors that will be affected. But we are talking about 40,000 (customers) initially and it could go up to 55,000 customers in the municipalities of Carolina, Canovanas and Rio Grande”he pointed Gary SotoDirector of Operations at LUMA Energy, who specified that subscribers from surrounding towns, such as San Juan and Trujillo Alto, will not suffer interruptions linked to Sunday’s work because “they are fed by other substations.”
Saca, for his part, commented that the repair projects at the Sabana Llana substation represent the “most complex” improvement in “the last 20 to 25 years.” At the beginning of the month, the secretary of federal energy, Jennifer Granholmvisited the substation as part of his official trip to Puerto Rico, in which he met with government officials and executives of private network operators regarding the status of the modernization of the electrical system.
At the moment, LUMA Energy directs projects in 15 electrical substations with subsidies which, according to company data, amount to $143 million. Soto described the Sabana Llana facility as one of the 10 most important in the system, since it transmits energy from the metropolitan area – where most of the consumption is concentrated – to the northeast region of the country.
As part of the work at the substation, Six switches or “machetes” will be replaced, including three on the 230,000 volt line and the same number on the 115,000 volt line.
Soto was emphatic in ensuring that no critical facilities, such as hospitals and health centers, will suffer interruptions on Sunday as a result of the work.
“In the figure that the island’s distribution system is configured, you can have feeders that (serve) two clients, as you can have feeders that have 5,000 clients. There are certain feeders with critical loads that usually have few clients for this reason, to be able to keep them in service in situations like this,” said the engineer, who was accompanied by the director of the San Juan region of LUMA Energy, Juan Oyola.
On the other hand, the Director of Communications of LUMA, Hugo Sorrentiniindicated that The consortium is “very close” to developing a system that allows customers to be contacted directly to alert them in advance of scheduled service interruptions.a component that was one of Saca’s promises when he assumed the presidency of the company last July.