LUMA Energy and 10 private developers met, before midnight on Friday, the conditions required for 11 photovoltaic energy farms to proceed to the construction and interconnection phases that, in accordance with contractual provisions, must have been completed, in most cases , for September 2025.
The president of the Governing Board of the Electric Power Authority (AEE), Francisco Berrios Portela, reported that, before Thursday, the interconnection agreements and other “subsequent conditions” had already been finalized for eight of the 11 planned works. Although he withheld the names of the proponents who had already signed the interconnection agreement and fulfilled all the conditions, he confirmed that the two solar projects of Clean Flexible Energy –a subsidiary of AES– were among the three remaining pending.
At the beginning of November, only the conditions of four solar projects had been finalized: Solaner Puerto Rico (San German), Yabucoa Solar, Convergent Coamo and Go Green USA (Yabucoa). Therefore, the agreements corresponding to Tetris Power (Arecibo), Pattern Barceloneta, CS-UR Juncos PV, Guayama Solar and Ciro Two Salinas, in addition to Clean Flexible Energy, had not yet materialized. LUMA confirmed this Friday that closure had been achieved with all the proponents.
“The issue of interconnections has already been resolved with all the developers, so they are in a position to sign”said Berrios Portela, in an interview on Thursday with The new dayin which he insisted that PREPA had not granted additional extensions to the deadline.
Through the interconnection agreements, in summary, the costs of the facilities that LUMA will build to enable the transportation of energy from the generation projects to the transmission lines operated by the consortium are stipulated.
The 11 projects, approved by the Puerto Rico Energy Bureau (NEPR) from 2022, will add 855 megawatts (MW) of capacity. The project with the highest generating capacity is CS-UR Juncos (125 MW), followed by Clean Flexible Energy Aguirre (120), Go Green USA (100), Convergent Coamo (100), Clean Flexible Energy Jobos (80.35), Pattern Barceloneta ( 70), Ciro Two Salinas (68), Guayama Solar (50), Tetris Power (45), Solaner Puerto Rico (40) and YFN Yabucoa (32.1).
With the exception of Clean Flexible Energy – which has until November 30, 2025 –, All projects in this first NEPR-mandated procurement round must begin injecting energy into the grid on or before September 30 of that year..
Clean Flexible Energy also has two battery energy storage projects with 100 MW of capacity each, while Convergent has three projects – in Penuelas, Caguas and Ponce – that add up to 150 MW of storage.
Although most projects will only have 22 months to begin operations – instead of the 24 months originally planned – Berrios Portela expressed confidence that it will be possible to complete construction within the established term. “These waivers were granted at the end of September, under the consideration that they were administrative issues that were pending, and we did not want the contracts to fall due to administrative issues”said the assistant secretary of Energy Affairs of La Fortaleza.
An additional project, called Emerald Solar Farmwas canceled after the Fiscal Oversight Board rejected the cost of energy sales agreed in June and, in a letter dated November 24, discarded the contractual amendments that were introduced later, arguing that they constituted an undue advantage for the proponent in relation to the other developers. Esmeralda Solar Farm would have generated up to 60 MW.
Customers will absorb cost increases
The amendments that were approved, in the first half of the year, increased the costs of energy sales by 34% compared to the original versions of the contracts, which will impact the rates that consumers will eventually pay. In interview with The new dayLUMA’s chief regulatory officer, Mario Hurtadoexpressed that increases in negotiated interconnection costs will also impact rates, since energy production expenses will be considered.
“Generation costs are recovered under the PPCA (‘Power Purchase Cost Adjustment’), and these projects, like all those that already exist, are going to be part of that mechanism, and Energy sector costs are ultimately recovered from customers. In this case, it will also be like that.”Hurtado stated.
The LUMA executive recalled that, to a large extent, the obstacles to finalizing the contractual conditions responded to factors such as global inflation and problems in supply chains, with their consequent increases in the costs of materials and equipment for the development of the works. .
“It is important to understand that interconnection is only one part of many elements of these projects and has never been an obstacle to the completion of execution”Hurtado argued. “We have always been working hand in hand with PREPA and other developers. “These are technical agreements and the difficult terms, as in all businesses, are always the economic ones.”
For his part, Berrios Portela pointed out that he does not know how many of the 10 developers will access the loans from the Federal Department of Energybut indicated that, to date, no transaction has been finalized, considering that PREPA would have to intervene in some of the approval stages.