The consortium LUMA Energy confirmed this Saturday that the repairs that will be carried out tomorrow, Sunday, at the Sabana Llana substation, in Carolina, remain in place, as well as the scheduled interruptions that are anticipated for three municipalities that use the facility.
According to the consortium, between 40,000 and 55,000 customers in Carolina, Canovanas and Rio Grande would lose service between 1:00 am and 3:00 pm on Sunday, while work is completed to replace switches at the substation.
“This morning (Saturday) we met again, all the teams reviewed the plans and we are still standing. (The jobs) already appear in the Planned Improvements portal table“, stated the Director of Communications of LUMA, Hugo Sorrentini.
On Thursday, at a press conference, the president of LUMA, Juan Sacaand operating officials of the consortium insisted that the works – which are part of federal projects aimed at improving electrical substations – will have a substantial effect on the quality of long-term service in towns as distant as Manati and Humacao, which They cover more than half of the country’s consumers.
Gary Soto, Director of Operations at LUMA, assured that the interruptions linked to the improvements will be limited to the three announced municipalities, since surrounding towns, such as San Juan and Trujillo Alto, are served by different substations. Likewise, he emphasized that no critical facilities, such as hospitals and health centers, will suffer interruptions on Sunday as a result of the work.