:format(jpeg):focal(3995x635:4005x625)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/6FRZWIRPPBH4FLQRVVBEECKMS4.jpg)
The president of LUMA Energy, Juan Sacaand the executive director of the Central Office of Recovery, Reconstruction and Resilience (COR3, in English), Manuel Laboyresponded this Tuesday to recent criticism from the resident commissioner, Jennifer Gonzalezfocused on the massive vegetation clearing project that the consortium hopes to begin executing early in 2024.
“LUMA respects the political process of Puerto Rico and the opinions that (Gonzalez) may have. Our focus is on Puerto Ricans and the companies that make Puerto Rico what it is,” Saca said regarding the resident commissioner’s statements.
Regarding the initiative, he pointed out that “the answer I have for Puerto Ricans and businesses is that, if we look at the exact facts, the clearance is an approval in which we, as LUMA, have applied, it has been approved and there are (funds ) specifically for clearing, they are not assigned for any other topic”.
“What has happened behind that in the political process? In reality, it is not something that concerns me,” the executive insisted in relation to the expressions of Gonzalez, who will challenge the governor. Pedro Pierluisi for the candidacy for the highest elective position in the New Progressive Party.
During a press conference in recent days, Gonzalez expressed that, although he considers vegetation management to be an important component of the stability of electrical service, federal funds should be allocated to “improve electrical infrastructure,” specifically listing substations, generation plants and transmission and distribution lines.
The vegetation clearing effort – which involves cutting trees along 16,000 miles of electrical transmission and distribution infrastructure – will cost nearly $1.2 billion and will run through at least 2026.
For its part, Laboy was categorical in rejecting that the funds allocated to the clearance program subtract resources from other projects in the electrical system.
The executive director of COR3 specified that the allocation of $11.4 billion that the Federal Emergency Management Agency (FEMA) announced in September 2020 – three years after Hurricane Maria – it only included funds for permanent works projects financed under section 428, so it did not contain items under section 406, which pays for disaster mitigation works. risks.
“This mitigation item 406, FEMA evaluates it together with the COR3, LUMA enters the arena and downloads a letter in January 2023, which establishes the framework to add the item of (funds) 406 to those $10,500 million (allocated since 2020), which is to mitigate risks, future damage and resilience. They are the famous additional $6,000 (million) to $7,000 million that are written in a letter from FEMA,” the engineer said.
In the letter, “parameters are established for what measures or activities are eligible to access these funds, project by project, precisely to be more resilient,” Laboy reaffirmed. “The clearing of vegetation, FEMA validates that it is an eligible activity under this additional activity that has nothing to do with 2020 and that, in effect, will mitigate over 70% of the interruptions that are experienced today”assured the official.