The Federal Emergency Management Agency (FEMA, in English) recently gave way to four reconstruction projects for the electric generation fleet amounting to $1,649 million, including an initiative to install energy storage batteries that, according to Generate PRwill reduce load relays by 90% once they are in operation.
Through the storage project, at an estimated cost of $650 million, batteries will be placed in nine facilities operated by Genera PR, including the Aguirre (Salinas), Palo Seco (Toa Baja), Costa Sur (Guayanilla) and San Juan plants. . Other batteries – with the capacity to inject one megawatt (MW) each for four hours – will be located next to rapid response units in Daguao (Naguabo), Jobos (Guayama), Yabucoa, Cambalache (Arecibo) and Vega Baja.
Total, Genera PR plans to acquire 430 batteries which, together, represent a capacity similar to that of a large-capacity power plant.
According to the company spokesperson, Ivan Baezthe expectation is that the first systems will begin operating in approximately two years, although the project includes separate bidding processes for the acquisition and installation of the batteries.
The batteries, said the executive, They will offer “immediate response if there is any problem in generation, they avoid blackouts in the generation system, they have ‘blackstart’ capacity (re-energizing the plants after a blackout) and reduce ‘load sheddings’ by 90 %”.
The project in the hands of Genera PR would be executed in parallel with another proposal from LUMA Energy –transmission and distribution operator– for the installation of batteries that, at present, is under consideration by the Puerto Rico Energy Bureau (NEPR). As recently as Monday, the NEPR granted the consortium until December 21 to respond if its project would be compatible with the initiative led by the company in charge of the generation system.
From the point of view of Genera PR, storage batteries are one of the key components for the stabilization and modernization of the generating flora, along with the replacement of emergency units (“speakers”) and the repair and replacement of equipment. “critical” on the main floors.
Replacing “speakers”
Another of the FEMA assignments that Baez highlighted were the $800 million for the replacement of “speakers”a project for which, at present, Genera PR receives proposals from up to eight bidders.
That project was amended by the NEPR, which ordered the company to reduce the generation capacity of the units compared to the operator’s original proposal. Initially, Genera PR requested authorization to acquire new units with up to 320 MW of capacity, but the NEPR established that only “speakers” of up to 200 MW could be installed, along with “blackstart” units of 81 MW.
Both the battery project and the emergency units were processed under the section 406 of the Stafford Act, which governs FEMA processes and provides for hazard mitigation works
Under the section 428 of permanent work, meanwhile, FEMA authorized $124 million for the purchase of “critical components” for the generation units. Genera PR, for months, has insisted that the replacement of parts is necessary to reduce forced plant exits by half by the end of 2024.
The company, however, has conditioned that deadline on the federal government agreeing to extend the permanence of the megagenerators located at the San Juan and Palo Seco plants – with a capacity of up to 350 MW – beyond March 2024.
“This (project) is for the purchase of critical parts; “motors, valves, things that had not been changed for decades, and they will be able to stabilize the plants”Baez emphasized.
Another item of $75 million – also under section 428 – will allow Genera PR acquire equipment to improve the “efficiency” of the plantswhich means reducing the amount of fuel needed to produce energy.
Baez assured that the cost efficiencies produced from that project may be claimed as part of the economic incentives that Genera PR, by contractual provision, can receive annually. Under the privatization pact, half of the savings are credited to Genera PR’s bonus calculation and the other half to consumers through the invoice.