Generate PRoperator of the generating fleet of the Electric Power Authority (AEE), recognized this Thursday that the funds directed to two of its main reconstruction projects have not yet been approved by the Federal Emergency Management Agency (FEMA, in English), contrary to what it had reported on Wednesday.
“They are projects that are in the approval stage, this is what they have told us and we trust that they will be approved”expressed Ivan Baezcompany spokesperson.
On Wednesday, Genera PR indicated that FEMA had given the go-ahead to four projects that total estimated costs of $1,649 million. The two main initiatives within that total include the replacement of emergency generating units, for an amount of $800 million, and a project to install energy storage batteries with the capacity to inject up to 430 megawatts (MW) into the grid, valued preliminarily at $650 million.
The other two projects announced by Genera PR are related to the acquisition and installation of “critical components” in the generating plants ($124 million) and works to improve efficiency in the operation of the fleet ($75 million).
Andres Garcia Martinoalternate FEMA recovery coordinator in Puerto Rico, clarified that The federal agency is still evaluating a request from Genera PR to amend the “speakers” replacement project with respect to the version that was approved earlier in 2023, before the transition between PREPA and the private operator was completed. The project that was approved by PREPA gave rise to the purchase and installation of seven rapid response units and four “blackstart” units (with the capacity to turn on after a general blackout), at a cost of $280 million.
After taking over as operator, Genera PR requested that the project be processed under section 406 of the Stafford Law, instead of section 404, as PREPA had been authorized to do. Meanwhile, Genera PR published the request for proposals (RFP) for the purchase of the units. The eight bidders that responded to the RFP must submit their proposals on or before January 8, 2024.
“The 404 fund has a deadline for projects submitted under that section, which is available to both municipalities and other government agencies, not just PREPA. The (deadline) date was October last year and the government, through the COR3 (Central Office of Recovery, Reconstruction and Resilience) presented a list of projects that exceeds the (allocations) limit.. To the extent that projects can be removed from 404 and moved to 406, money is freed up that can be used on other projects on the waiting list that were submitted on time,” said the FEMA official.
Under 406, in addition, “additional needs could be evaluated that, when originally presented (as 404), were not contemplated,” Garcia Martino added.
Baez declared to The new day that Genera PR would not comment on the decision to request the amendmentwhile pointing out that the increase in costs compared to the version approved by FEMA responded to the analysis of the needs carried out by the company.
According to Garcia Martino, FEMA should make a determination on the speaker amendment in early 2024. “That has not been approved.”. Just today (Thursday), there were technical meetings, because moving it from 404 to 406 is not a letter. The project must be defined in such a way that it meets the 406 criteria, which are more rigorous, because they require that it be tied to damage caused by the Hurricane Maria”, clarified the FEMA official.
Garcia Martino, on the other hand, pointed out that FEMA expects to launch the battery procurement project between the end of this year and January 2024.
“We are close. Soon, Genera must present the battery installation project for us to then evaluate that part. We do not foresee major issues, but we need to see that description,” said Garcia Martino.
On Wednesday, Genera PR indicated – in a written summary – that FEMA had “approved” the “equipment purchase” for the four projects.
At that time, Baez described the $1,649 million as a “historic approval to help stabilize the island’s generation issue.”