:format(jpeg):focal(4781x1488:4791x1478)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/ZHYPGT5MTRBUJMTJAM3LVFTQ5M.jpg)
Generate PR complied with the term granted by the Energy Bureau (NEPR) to submit his savings plan for the purchase of fuel, but he delivered it confidentially, for which reason the regulatory body required him to justify his position through a legal memorandum in o before Friday.
From an order issued yesterday by the PREB, it appears that Genera PR presented a “draft” of the document last Sunday, one day before the expiration of the term that the agency had established on June 30.
“As part of its filing, Genera affirms that the Fuel Optimization Plan contains privileged and confidential information in accordance with section 6.15 of Law 57-2014”indicates the PREB document.
The fuel purchase plan is a key component of LUMA’s operations, since half of the savings it manages to produce would be credited to the pot of annual economic incentives amounting to $100 million, and the rest would represent savings in the rate for the consumers.
Although Genera has not specified the scope of the savings from the purchase of fuel, last May the president of the company, Brannen McElmurrayestimated that spending could be reduced between 10% and 15% compared to what the Electric Power Authority (PREPA) has historically maintained.
The purchase of fuel represents the main expense of the electrical system, around $3,000 million annually, so savings close to McElmurray’s projections would mean savings of around $300 million.
Two weeks ago, Genera’s spokesman, Ivan Baez, specified that PREPA’s main fuel supply contracts expire in November, for which reason the company expects to enter into negotiations over the next few months. In this sense, Baez also minimized the fact that there was no approved savings plan when Genera took office on July 1.
On Friday, in addition to presenting the memorandum that justifies the confidentiality of certain information in the draft of the savings plan, Genera must submit a redacted version that will be made public, indicates the PREB order.
“The memorandum must include a table that identifies the confidential information, a summary of the legal basis for the confidentiality designation (and) why each claim or designation is applicable to the confidentiality legal basis,” the agency listed in the signed order. by four of the five commissioners: President Edison Aviles and associates Lillian Mateo Santos, Sylvia Ugarte Araujo and Antonio Torres Miranda.
Associate Commissioner Ferdinand Ramos Soegaard did not intervene.