The General Archive of Puerto Rico already has electricity

The General Archive of Puerto Rico already has electricity

He Institute of Puerto Rican Culture (ICP) announced today, Friday, that the building that serves as headquarters to the General Archive of Puerto Rico and the National Library of Puerto Rico already have electricity service.

According to official statements, after a long and complex process, the ICP managed to install the necessary equipment so that the Dr. Ricardo Alegria Gallardo building in Puerta de Tierra can receive energy without the help of a generator. Originally, it was reported that this process could take up to several months.

The new day had previously reported that a complex electrical fault had left the General Archive without power after the substation that fed the building was severely affected by the rains of October 27.

“We were operating with an emergency plant. That plant was fixed. When the electricity service arrives on Monday, we realize that the plant was operating, we were not directly connected to electricity. It’s called LUMA, it’s called everyone. They do the investigations and it turns out that when the electricity service came again, in quotes, it burned up the substation, which is what connects the street service to the building,” the ICP deputy director had explained. Freddy Velez Garciain interview.

Since the situation was made public, several employees, officials, academics and citizens in general have expressed concerns about the well-being of the documents and other historical contents housed in the Archive, which is custodian of some of the documentary, film and musical collections. most important in the country.

“The investment that has been made to protect our heritage in a month and two weeks has been substantial because the urgency and importance of this building is recognized and no effort has been made in making the investment that is needed to maintain this heritage of safely and to be able to reopen the Archive and the National Library as soon as possible. But always taking precautionary measures and doing so according to the best standards that exist,” he said. Hilda Teresa Ayala Gonzalezdirector of the General Archive, about the efforts to address this emergency in an interview on December 5.

The archivist had explained the Institute’s plan in detail, and emphasized the importance of proceeding carefully with each of the phases. According to Ayala Gonzalez, the air conditioning process, for example, must be well planned and must be carried out little by little, since the contents of the building are, for the most part, organic materials that are extremely sensitive to drastic changes in temperatures and humidity. “We have to do this gradually, with great caution, to ensure that those documents that have not been affected up to this point can return to their normal state,” she said.

According to a statement from the ICP, because the building is already directly connected to the electrical energy service, this air conditioning phase can finally begin. The Institute estimates that in 10 days all areas of the building will reach a stable and adequate temperature, and then proceed to the last phase, which consists of cleaning the documents, work areas and the service spaces where employees are received. and researchers.

While this work is carried out, the building will remain closed to the public, as it has been since this issue affected the building.