Almost 11 months after having closed for the start of a monumental repair project, the Naranjito cable-stayed bridge will reopen two lanes to traffic on Wednesday night, one in each direction.
“The project is on schedule, and tomorrow (Thursday) citizens will be able to begin using the bridge normally, in both directions. “They don’t have to be aware of the schedule,” said the executive director of the Highways and Transportation Authority (ACT), Edwin Gonzalez Montalvoin an interview with The new day.
The bridge was closed on January 30 to begin repairs, which affected thousands of residents in Naranjito, Barranquitas, Comerio, Morovis and Toa Alta, who frequently travel through the emblematic structure, which now exhibits two repaired lanes without undulations.
In January, a journalistic investigation by this newspaper revealed irregularities and construction defects on the bridge. Two and a half months after closing it, The ACT opened, on April 18, a reversible laneafter studies concluded that the measure was viable while repairs continued, with the aim of serving vehicular traffic during peak hours in the morning and afternoon.
Gonzalez Montalvo explained that the modules used to create this reversible lane, according to peak hours, will be removed this Wednesday, so that, around midnight, the two lanes will be available for public use.
At the beginning of October, the ACT began to carry out one of the main phases of the repair: the placement of the fill – polymeric material – on the two lanes that will be reopened, eliminating the undulations that represented a construction and safety problem since its inauguration. .
“During the last few weeks, we were working with the epoxy material on the bridge, and demolitions were done. Every time one passed, data was taken, it was refined,” explained the director.
“The work that was done gives the user an experience of comfort, which will not have the undulations that, in turn, created the vibrations; That is going to be a thing of the past, the difference is from heaven to earth, it is a change,” Gonzalez Montalvo stressed.
The official expressed that it is not foreseen that these lanes will have to be closed for any repair or work on the rest of the structure. However, “if it were necessary in any phase of the project, it would be communicated to citizens in time so that they can organize themselves,” the engineer emphasized.
Once the two lanes are open – one in each direction -, the Ferrovial company, in charge of the project, will begin an administrative recess during the Christmas period, and work will resume after January 6, Three Kings’ Day.
“Now, we focus on the other two lanes,” said the head of the ACT, while revealing that a second subcontracted company works on maintaining the bridge stays. “The subcontractor Freyssinet has been working, the boots are being filled, each of the cables is being verified,” he explained.
Gonzalez Montalvo added that new signage will be placed to guide traffic. As for the repair of the other two lanes, the next step, once work resumes in January, is the demolition of the corrugations, “start shaving those top layers of the earthenware, see where we have to scrape a little more, finish with the final level and, on top of that, the polymeric material and the final layer would be placed,” he explained.
The ACT leadership envisions that the bridge will be ready, with its four lanes repaired and open to traffic, between July and August 2024. The estimated cost of repairs was initially estimated at about $26 million. “For now, costs remain the same,” said the executive director. Likewise, he said that the public agency is working on the request for proposals to hire a company specialized in the maintenance of this type of structure.
“We have been guided by experts in the area, companies that are experts in cable-stayed bridges, local companies of world caliber, experts in concrete and concrete, so that all the decisions that, at the end of the day, we are making are not due to political pressures, but rather that the data allows us to make informed decisions to be able to move forward”said Gonzalez Montalvo.
“Preventive maintenance is key, with the necessary frequency, to ensure that the useful life of the asset, the bridge, can be extended. We have had those lessons learned,” he pointed out.