FEMA rejects government request to fund temporary generation until November 2024

FEMA rejects government request to fund temporary generation until November 2024

The Federal Emergency Management Agency (FEMAin English) rejected the request of the government of Puerto Rico to pay, until November 2024, for the operation of the 15 temporary electricity generation units that it installed in several plants after the passage of the Hurricane Fionathe governor reported Pedro Pierluisi.

Instead, the first executive noted, FEMA is evaluating whether to acquire or rent the equipment – ​​which is now in private hands – so that the government of Puerto Rico can continue using it.

Pierluisi, in an interview with The new day On the occasion of the end of the year, he was emphatic that, if the electrical system does not have these generators, starting in the summer of 2024, citizens will once again experience frequent interruptions or blackouts.

“FEMA has already made the decision that, as of March 16, it will not continue paying for the operation of the generators. That is, the expense, the fuel consumption of those generators, that decision has already been made.”said.

“What FEMA is evaluating, at our request, is providing us with funds to either acquire the generators or rent the generators, which are available for use by the community. Electric Power Authority (AEE); Generate (PR) would be (who would be in charge), obviously,” he added, after specifying that, in the future, PREPA would pay for the fuel for the generators with the income that, ordinarily, is received from customers through the electricity bill. light.

What would happen if one of the scenarios you describe is not achieved? Would the interruptions in the electrical service return?, he asked The new day.

“If that does not happen, we could have interruptions in the summer, because we already suffered it last summer”acknowledged the president.

After Hurricane Fiona hit – in September 2022 – and faced with a deficiency in generation compared to energy demand, FEMA assisted the government of Puerto Rico with portable generators. Then, a task force was created to stabilize the electrical grid, and FEMA had announced that generation units and barges would be installed that would provide Puerto Rico with a total of 700 megawatts.

However, after repairs that PREPA made to its fleet, FEMA senior management informed the government that they would no longer install generators to cover 700 megawatts, but half.

After FEMA’s change, Pierluisi asked for a reconsideration. FEMA chose to leave the generators until March 2024, although the initial date was last November, to coincide with the end of the Hurricane season. The governor’s request, in his reconsideration, was that FEMA pay for the operation of the equipment until the end of the next hurricane season.

According to FEMA, the commitment with the government of Puerto Rico to leave the generators, until next March, involves an investment of $1.5 billion in the location, maintenance and operation of the 15 unitswhich provide an extra 350 megawatts to the grid.

Additionally, FEMA had reported that, as of last September, there were disbursed $150 million to pay bills submitted by the United States Army Corps of Engineers, a department entrusted with reinforcing local generation in the midst of hurricane season.