The executive director of the Electric Power Authority (AEE), Joshua Columbusurged the Puerto Rico Energy Bureau (NEPR) to urgently attend to and approve the request for the acquisition of temporary generating units with the capacity to supply up to 350 megawatts (MW) of energy, a call that seems to conflict with the schedule established in the most recent resolution of the regulatory body .
Colon stressed that it is urgent that the NEPR endorse, no later than the end of January, the purchase of the 17 megagenerators installed in the San Juan and Palo Seco (Toa Baja) plants, which would facilitate the continuity of their operations after December 15. March, when the federal government will stop financing electricity production.
“This problem must be resolved today. It has been shown that these units have largely mitigated blackouts and service interruptions due to generation failures or insufficiencies, for whatever reasons. They managed to convince the federal government to look for an alternative and that was a success,” Colon pointed out in an interview with The new day. “March 15 is just around the corner. “I don’t like to impose any conditions, but I hope we can finish this with the NEPR before the end of the month.”he stressed.
LUMA Energy has estimated that, between June and October 2023, the generators avoided more than 40 load relays due to lack of electricity production. The 350 MW represent more than 10% of the peak demand recorded in the summer months.
On Friday – after The new day spoke with Columbus -, The NEPR released a resolution and order in which it stated that “it is not in a position to evaluate PREPA’s request to approve the scope of work to transfer ownership of the temporary units.”” to the public corporation.
Before committing funds to projects in the electrical system, the Federal Emergency Management Agency (FEMA, in English) requires that the NEPR certify that the works comply with the state public policy for the energy sector. In the case of the purchase of the megagenerators, FEMA has established that it is a project eligible for 90% financing, complemented by a 10% state match, which government officials have anticipated would come from the Disaster Community Development Block Grants (CDBG-DR, in English).
(Xavier Araujo)
In Friday’s resolution, the NEPR granted PREPA, LUMA and Generate PR 10 business days to identify “the sources of financing for the acquisition of the equipment and/or outline potential financing scenarios.” In that same term – which expires at the beginning of February – the three entities They will have to report how the acquisition of the units “would alter federally funded projects previously approved by the NEPR.”
The NEPR based its concerns mainly on the fact that, under the regulations that govern public-private alliances and public energy policy, “the PREPA may only conduct transactions related to the generation, distribution, transmission and measurement of electrical energy, as well as any another function, service or facility, through alliance contracts”, which in turn are regulated by the Public Private Partnerships Authority (AAPP).
In recent days, the executive director of the AAPP, Fermin Fontanespointed out that it is envisioned that Genera PR – through an amendment to its privatization contract – will be responsible for the operation and maintenance of the temporary generators, although the company will not be able to intervene in the negotiations for the acquisition because it is a subsidiary of New Fortress Energywhich is the owner or lessee of the equipment that PREPA intends to purchase.
Although other officials such as Fontanes and the executive director of the Central Office of Recovery, Reconstruction and Resilience, Manuel Laboyhave stressed that the acquisition of the generators is not intended to add long-term electrical production capacity, but rather to serve as a bridge for Genera PR to complete major repairs on the deteriorated fleet it operates, Colon expressed himself in a different tone.
“What we are pursuing is to acquire these units so that they operate permanently for the benefit of the people of Puerto Rico”said Colon, answering in the affirmative to the question of whether that meant until the end of the units’ useful life.
Previously, the NEPR has denied a series of repair investments in the existing fleet, stating that extending the useful life of the thermoelectric generation infrastructure is inconsistent with the transition to renewable sources contemplated in law and the Integrated Resource Plan.
:format(jpeg)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/TMKF3MMMVREVRNZUITWNSGSJYM.jpg)
While the units installed by the federal government have been kept on regularly since last summer, Colon acknowledged that Its function could evolve if Genera PR manages to increase the capacity of the main plants at the Aguirre (Salinas), Costa Sur (Guayanilla), San Juan and Palo Seco plants.
“When the base units are repaired, at some point (the megagenerators) will serve as a response capacity to breakdowns and also to help the integration of renewable energy,” he noted.
Colon stressed that, in addition to having sufficient capacity to meet demand, to avoid load shifts, it is necessary to have nearly 700 MW in reserve in case any unit goes out of service unexpectedly.
“No machine (generating unit) will go out of service until its replacement is available. “How are you going to turn something off and abandon it for maintenance if you don’t have the replacement?” he questioned.