After last December a report by the Puerto Rico Energy Bureau (NEPR) will reveal a mixed balance in the performance metrics of LUMA Energythe private operator, in charge of the transmission and distribution of the electrical system of the Electric Power Authority (AEE), announced Tuesday that its most recent report to the regulator highlights improvements made in several key areas of the network.
According to the energy consortium, In the second quarter of 2023, there was a reduction of 25 million minutes in service interruptions thanks to the installation of 3,500 automated devices. Smart devices, they indicated, are used to reduce the impact and duration of outages, a press release sent by the government contractor indicates.
Likewise, the document indicates, Additional improvements were evaluated in several areas of the system such as security, duration and frequency of service interruptions compared to previous carrier metrics.
The previous report delivered to the NEPR, released on December 22, highlighted that between July 2022 and June 2023, the average time that LUMA customers were without electricity service had amounted to 1,218 minutes.
Nevertheless, The metric (SAIDI) only considers service failures associated with breakdowns in the transmission and distribution network operated by the consortium, therefore it excludes load shifts caused by electricity generation deficiencies.which until June 30 was in the hands of the AEE and, since then, of the company Generate PR.
“In the past quarter, LUMA continued to make progress across several metrics. For example, The company’s efforts to install thousands of automated devices have helped our customers by reducing millions of minutes of service interruptions. Without these devices, customers would have been left without electrical service,” he said. Juan Sacapresident and chief executive officer of LUMA in the statement.
“In terms of the frequency of interruptions, although we are proud that our performance is better than that of the previous operator, The impact of vegetation on service reliability demonstrates the need to improve our maintenance work and the importance of the new Vegetation Clearance Initiative”he added.
The report further notes that, During the second quarter, LUMA achieved a 26% reduction in service interruptions compared to PREPA.
Furthermore, it was indicated that it was achieved a reduction of 25 million minutes in service interruptions experienced by customers thanks to the installation of over 3,500 automated devices. This is equivalent to an average of eight million fewer minutes per month in this last quarter.
Daniel Hernandez Morales, vice president of operations at Genera PRcompany in charge of grid energy generation, which in turn transmits and distributes LUMA Energy, expressed concern in early January about raising available power capacity in time for next summerwhen demand increases and, consequently, the risk of selective blackouts due to lack of production.
In interview with The new dayHernandez Morales pointed out, on December 22, that Among the plants that have not yet undergone repairs are unit number 6 of the plant South coast, in Guayanillawhich remains operating because the maintenance and repair work in unit number 5 of that plant has not been completed.
Originally, the management employee said, unit 5 was anticipated to return to service in October 2023, but that did not happen.
According to the engineer, The delay in repairs is due to the fact that the number of breaks identified in the boiler was greater than what was anticipated last July, when it went out for maintenance.
The jobs scheduled in South Coast 6he indicated, They were to be completed by the beginning of Februarybut is now expected to return to service in March 2024.
Costa Sur unit number 1, however, has been out of service since before Hurricane Fiona, in September 2022. Although Genera PR hoped to return it to service by the end of 2023, Hernandez Morales acknowledged that faults found in the cooling system will postpone its restoration for at least an additional month.
“We all understand that this must be the reason why The system did not have sufficient capacity to be energized. The insulation tests on the generator did not present acceptable parameters and it was concluded that it is because of that ‘liquicity’ that the generator still has.. “We are in the process of working on it with the people at General Electric and, in the next three weeks, we should be completing the repair,” the engineer said about the unit with a nominal capacity of 450 MW, the largest in the system.