LUMA Energy points out data deficiencies as an obstacle to developing the Integrated Resource Plan

LUMA Energy points out data deficiencies as an obstacle to developing the Integrated Resource Plan

In view of the review of the Integrated Resource Plan (PIR) of the electrical sector, LUMA Energy He insisted this Tuesday that it is urgent to develop digital models that allow replicating “the physical system” in order to optimize network planning procedures.

“The historical records that we used were very different from reality. A line could sustain only 50% (of the electrical load) of what the records indicated. It is one of the challenges we face to propose a justifiable model”stated the director of LUMA Network Planning, Daniel Huttonin a technical view in the Puerto Rico Energy Bureau (NEPR).

According to Hutton, without an inventory of all the assets that make up the electrical transmission and distribution networks, it is not possible to create a digital model that faithfully replicates the real functioning of the system which, in turn, allows adequately defining the necessary investments in the future.

Kumneger Media
Kumneger Media
Kumneger Media is a News and Entertainment Website & Channel. Kumneger Media in addition to News and Entertainment it is the hub of Politics, Movies, Drama, Music, Comedy, Documentary and More!