The selective blackouts that have left tens of thousands of customers without power over the past few nights will last, at least, until the cogenerator PREPA Puerto Ricoin Guayama, managed to return its two units to service, with the capacity to produce 454 megawatts (MW), or close to 15% of the daily peak demand.

“We went up (unit #3 of) Palo Seco yesterday (Tuesday). Now, it is a matter of AES being able to enter the system”said this morning, Wednesday, ivan baezspokesperson for Generate PR.

On its official website, LUMA Energy forecasts a demand of 2,922 MW for this Wednesday night, which would exceed the available generation by 146 MW. As of 8:00 pm yesterday, more than 108,000 consumers remained without service due to generation deficiencies, including more than 27,000 in the Caguas region and another 24,000 in San Juan.

At the time of this publication, AES had not informed The new day when the return of its two units, which have been out of service since July 15, was projected. Last month, AES announced that, at the request of LUMA, it would postpone preventive maintenance on its #2 unit until the end of September, in an effort to ensure the highest amount of generation available in the months of peak consumption.

Among the base units that Genera PR operates, South Shore #5in Guayanilla, is turned off as part of its preventive maintenance program, a decision that Baez defended.

“Costa Sur is going to take several months to do this preventive maintenance, because it definitely has to be done. (Otherwise) you could suffer irreversible damage.”affirmed the executive of Genera.

Units #5 and #6 of Costa Sur have an installed capacity of 410 MW each.

Given the current scenario, Baez stressed that it is urgent that the federal government agree to increase temporary generation from 350 MW to 700 MW through portable megagenerators.

“It gives rise to the claim that both the government and the private sector have made, that those additional 350 MW of temporary generation are needed to be able to provide this preventive maintenance to the plants and the replacement and modification of components”Baez said.

“Unfortunately, as system operators, we have no control over generation. We are in communication with Genera and the other private companies that provide energy. We will be monitoring the situation and reporting what we see,” said LUMA Communications Director Hugo Sorrentini. “If we have a generation deficit, we could experience load relief again.”