Toa Alta – During an official event on Thursday by the governor Pedro Pierluisi, the mayor of this town, Clemente “Chito” August, He unbuttoned the shirt he was wearing to reveal a “t-shirt” that He had a message for the president: “Toa Alta needs ‘Las Curvas’ 861 open now”.
This was the peculiar way that Agosto, of the Popular Democratic Party (PPD), chose to confront the chief executive and demand the immediate opening of the PR-861 highwaywhich has remained closed since the passage of Hurricane Fionain September 2022.
“What we want is for them to open PR-861. “The people are already tired”said the mayor, who denounced that the construction work on the road is going “at an ant’s pace.”
Showing the message he wore on a “t-shirt” under his shirt, he deplored that, initially, the Pierluisi administration promised that the highway, known as “Las Curvas”, would be reopened by December 2023. Agosto spoke out while Pierluisi answered questions from the press after the inauguration of the rehabilitation work at the Enrique Ortega filter plant.
In response to the mayor, The governor attributed the delays in the work to “situations caused, precisely, by issues of weather, climate, situations that have arisen, but work is being done responsibly.”.
“That road was highly impacted by the hurricanes and has had a series of collapses, including in the middle of the construction itself. But measures have been taken to repair it. Likewise, a bridge that is very close to that road is being repaired, which I have also inspected,” he noted.
The first executive reported that the estimated cost of the project amounts to $7.7 million, from the Federal Highway Administration. He added that as a result of “new landslides” in the area, the allocation was raised by $2.5 million, for a total amount of $10.2 million.
The construction work is carried out from kilometer 7.2 of the highway to kilometer 8.8, reported the president, who added that the works include the stabilization of a slope that “was recently affected.”
“I understand the mayor’s claim, because any mayor would make the same claim. It is an important road that basically connects Toa Alta with Bayamonand now it means that people have to spend at least half an hour longer traveling. That generates citizen annoyance, but I attest that the work is being done with professionalism and the efficiency that should be done,” argued Pierluisi.
The governor did not specify when the road will reopen, but stated that He expects the work to be completed “in the coming months”.