Due to errors of a “clerical” nature on the part of the contractor in the processing of a permit, the beginning of the demolition of 18 homes adjacent to the Piedras Riverin the Puerto Nuevo urbanization, in San Juanis detained until further notice, reported this Tuesday the United States Army Corps of Engineers (USACE, in English), in charge of the controversial channeling project for the body of water.
Maricarmen Crespohead of the USACE Construction Division in Puerto Rico, stressed that the execution of the demolitions is not at risk, although It is unknown when work could begin on 25th Street in the development, where the row of residences that will be impacted is located..
Initially, the USACE had announced that The mobilization of machinery and demolition work would begin in the week of February 26, but, since then, no movement has been observed in the area. Crespo specified that the contractor, All Phase Servicesreceived some information regarding its request for permits, at the same time that it must incorporate certain information into the sign installed at the construction site.
“We had to update a document (in the permit application) because they had made a mistake. The permit was resubmitted in OGPe (Office of Permit Management) and is continuing its course. Once it’s approved, we go outside. It is an administrative error; “It has nothing to do with the environmental issue, which is already in compliance, or with any contractor issue.”he stressed.
According to the federal official, the errors revolve around “two documents” that the contractor had to submit again to the OGPe. At the moment, the USACE could not specify how long the process before that agency would take.
“On the label, information requested by the regulations was missing, which I understand is the OGPe address and an email,” added the engineer, during a round table that the USACE organized to elaborate on the flood control project in the basin. of the Piedras River, which also encompasses communities further south of San Juan, such as University Gardens, Villa Nevarez, Jardines Metropolitanos and Reparto Metropolitano.
The flood control project in the Piedras River basin, work with an estimated cost of $2.7 billion – of which approximately $1.6 billion has been allocated by the Congress– would mean benefits for nearly 200,000 residents of the capital, but experts and community leaders have warned that the proposal ignores the advances in science since it was conceived in the 1980s, and that it will not meet its objective if it is not addressed. the sewers managed by the Municipality and the Department of Transportation and Public Works (DTOP).
During the round table, Crespo and the engineer Jose Bilbaohead of the Puerto Nuevo River Section of the “task force” that the USACE formed for Puerto Rico and Virgin Islandspointed out that the project has incorporated strategies to reduce the environmental impact, such as planting mangroves and eliminating the design of concrete floors in the canalized segments to maintain the natural background.
What’s next: demolition of a hundred structures
The subsequent phases of the canalization in the Puerto Nuevo area will require the acquisition of residential and commercial properties in the Metropolitan Reparto and Metropolitan Gardens sectorsa process that Bilbao estimated should begin before the end of 2024.
Once the design phase is completed, the USACE would provide the Department of Natural and Environmental Resources (DRNA) a “notification to proceed,” which would authorize the state agency to negotiate with the owners whose properties will be purchased. The USACE projects that more than a hundred structures will need to be obtained and demolished in that phase..
“Communication (with the DRNA) increases as construction approaches. The DRNA has the information from the beginning,” he said, for his part, Alexis Alejandrospecialist in the USACE Real Estate Office.
Although, two weeks ago, the Piedras River Basin Community Coalition demanded the creation of a “special development plan” that considers the consequences of channeling, Bilbao maintained that, in certain segments of the body of water – such as Jardines Metropolitanos and Reparto Metropolitano –, the engineering alternatives available to minimize the impacts are limited. floods.
Likewise, USACE officials ruled out that it is imperative to prepare a new environmental impact statement (DIA) to replace or update the one made in 1984. Since then, the federal agency has prepared environmental assessments, a document – narrower in scope than an EIS – that is required when design modifications are proposed.
The DIA, according to the head of USACE Planning in Puerto Rico, Nelson Colonwould be necessary if major changes to the project were proposed or substantial amendments were introduced to the National Environmental Public Policy Law.
“What happens is that this issue of an EIS versus an environmental evaluation is that they are based on the magnitude of the impacts. The EIS is from the 1980s because, at that time, the impacts of the project were evaluated in its entirety. Subsequent evaluations evaluate specific impacts of a phase,” Colon said.