The Fiscal Oversight Board (JSF) early on Friday night gave its approval to the transaction through which the continuity of the operations of the emergency generators that, since last year, have provided stability to the electrical production fleet and whose operation by the federal government ends at midnight.
Through a letter released after 6:00 pm, the Board authorized the budget amendment –of more than $30 million– that will allow the Electric Power Authority (AEE) cover the necessary matching for the purchase of the generating units. Likewise, it was expected that it would also give way to the contract for the supply of natural gasawarded in favor of New Fortress Energy (NFE), which has provided fuel to the federal government since last summer.
On Friday, however, it emerged that PREPA will only acquire 14 of the 17 units, which will reduce the available generation capacityparticularly in the event of potential breakdowns.
Without being able to guarantee that the units will remain in operation uninterruptedly from midnight, the spokesman for Generate PR, Ivan BaezI affirm that The adjustment in the transaction will mean a reduction in generation compared to the 350 megawatts (MW) of capacity that, until now, have been available.
“I understand that (the capacity will be) approximately 300 MW. It’s a little less, but right now, any megawatt counts“Baez told The new dayat a time when the generation reserve projected for Friday night stood at just 176 MW, according to LUMA Energy.
As part of the mission that Federal Emergency Management Agency (FEMA, in English) delegated to the United States Army Corps of Engineers (USACE, in English), seven units were installed at the Palo Seco plant (Toa Baja) and another 10 at the San Juan plant. In both, typically, they have operated leaving a unit as a backup, so The reduction in the generators purchased would limit the margin to respond to potential breakdowns.
The Assistant Secretary of Energy Affairs of Strength and president of the PREPA Governing Board, Francisco Berrios Portelanoted that the generators included in the transaction have a total capacity of approximately 350 MW, although not all will necessarily be on permanently.
“That capacity (for protection) is what we are not really going to have. We have validated that we will have the capacity to generate 350 MW. It is not an ideal situation, but it is still very important”said the engineer.
“We work based on what LUMA requires of us. LUMA’s economic office asks us and the other private generators to turn on (certain units),” Baez added.
The executive director of the Authority for Public Private Partnerships (AAPP), Fermin Fontanes Gomezspecified, for his part, that The three generating units that were left out of the transaction can produce up to 105 MW, since they are models with greater capacity than the other 14.
The uncertainty surrounding the transaction caused LUMA to ask the Puerto Rico Energy Bureaulate on Thursday night, an extension until March 22 to submit the rate adjustment request for the April to June quarter that was originally due to be submitted yesterday, Thursday.
Transaction for $306 million
In interview with The new dayFontanes Gomez explained that NFE – which in addition to supplying the fuel was the owner of the other machines – could not complete negotiations with a subcontractor to acquire the three generators and then transfer them to PREPA as part of the transaction valued at $306 million. FEMA will cover 90% of that amount and PREPA, the matching 10%, or just over $30.6 million.
Initially, it had been anticipated that the match would come from funds from the Disaster Community Development Block Grant (CDBG-DR, in English), but Fontanes Gomez indicated that an initial analysis, together with the Housing Department, concluded that it would not be possible to resort to that source. Berrios Portela maintained that the funds will come from available items in PREPA’s budget, although the possibility of eventually being reimbursed with CDBG-DR funds will continue to be studied.
Berrios Portela and Fontanes Gomez pointed out, separately, that The government will continue studying the possibility of acquiring the three generators that were left out of the transaction. FEMA approval contemplates the generators being used until the end of 2025.
On the other hand, although he reserved the figures, because it was a matter that was still before the Board, the head of the AAPP assured that The contract awarded to NFE for the supply of natural gas included “a better price than that of the Corps of Engineers”.
NFE is the parent company of Genera PR and also supplies the natural gas used in units #5 and #6 of the San Juan plant.
When asked if Genera PR would be in a position to assume the operation of the generators starting at midnight, Baez noted that there would be a “transition” in logistics.
“There is a team that is operating it (currently). I understand that this team would stay, one possibility (is that it was) subcontracted or that they are part of Genera. An orderly transition has to be made,” he said.
It is imperative to increase fleet capacity
On the other hand, Baez acknowledged that the instability in several fleet plants, such as unit #5 of Costa Sur (Guayanilla) – which has been going in and out of service in recent days –, keeps the risk of load shifts latent and highlights the urgency of having emergency generation.
“It will take days (to achieve stabilization), just like (with the unit) Aguirre #1. They go up (enter service), repairs begin and they are taken out. They are units that date back to the 60s. The risk of load shifts is always there. We have had to live with that, and the detail is how to minimize them. There is generation capacity, but, since the system is not automated, it takes 15 to 20 minutes for the backup units to turn on,” he stated.
“Now, facing the beginning (of the period) when demand continues to increase, important units have to enter, like Aguirre #1, which had entered and had a failure again,” said Berrios Portela. “It is an issue that we are asking Genera to make the corresponding adjustments so that the work can be accelerated. This week demand has increased almost 200 MW,” he warned.
Berrios Portela added that the government maintains a preliminary agreement with the Federal Environmental Protection Agency so that authorize the continuity of operations while the analyzes aimed at obtaining regulatory permits are concluded.