Generate PR awarded the cause of the departure of two units from the central south coaston Thursday night, due to failures in the substation that it manages LUMA Energy outside the generating facility, although the details of the breakdown were not yet known.
The service exit of units #5 and #6 of the plant, located in Guayanilla, threatens to force load shifts in view of the electricity demand expected for Friday nightOn Thursday night, nearly 90,000 subscribers lost service following problems in Costa Sur.
At the time of this publication, LUMA Energy only indicated that the breakdown was under investigation, so it was too early to assign the cause.
“It was a fault at the LUMA substation. We are waiting for them to resolve the problem so that they can put the Costa Sur plant back into service. The detail is something that they (LUMA) have to provide,” he said. Ivan BaezVice President of Public Affairs at Genera PR.
“We are waiting to put the units into service. They have to resolve the issue of their substation,” added the spokesman, who acknowledged that, without the production provided by Costa Sur, service cuts would most likely be required at night.
Units #5 and #6 of the plant can normally generate over 500 megawatts (MW). At around noon, LUMA projected that demand would reach around 3,050 MW on Friday night, but Available capacity would fall short by more than 100 MW, forcing the implementation of selective blackouts.
The generation deficiencies would occur despite the fact that, in the morning hours of Friday, unit #6 of the central San Juanwhich had been shut down since it suffered a failure more than four months ago, in an event that left nearly 200,000 customers without electricity.
“It is urgent, and obviously, the commitment is to increase the generation capacity. We have been gradually increasing it in the past months and stabilizing the system. In this specific case, we need (LUMA) to give us the ‘go’ (green light) to put the units back into service. We are going to try to get them in before the end of the day,” Baez added regarding the possibility that the plants in Costa Sur could be turned on at some point on Friday.
LUMA press spokesman, Hugo SorrentiniMeanwhile, he indicated that the consortium in charge of electricity transmission and distribution continues to inspect the Costa Sur substation. Also known as the “switch yard,” the substation is the same one that suffered a catastrophic failure on the night of April 6, 2022, causing a general blackout.
“It was a service interruption that lasted less than half an hour,” Sorrentini said, referring to the Thursday night event.