The start of classes in 31 public schools will be delayed by a week, because the schools will not be ready to receive students on Tuesday, August 13, announced the secretary of the Department of Education, Yanira Vega Roots.
There are 20 schools in the Caguas region, eight in the Bayamon region, one in the Humacao region, one in the San Juan region and one in the Mayaguez region.
The first day of classes for these 31 schools will therefore be on August 19, when the infrastructure work still being carried out is expected to be completed. Another school, the Eugenio Guerra Cruz Olympic Hostel (Ecedao) Specialized Sports School in Salinas, will receive its students on Sunday, August 18, since it is a residential school.
At the time of this publication, the Ministry of Education had not provided the complete list of schools. It was reported that each educational region has already disclosed the information to the school communities.
Nearly 100 schools will operate on reduced or alternating schedules
Meanwhile, another 90 schools across the seven educational regions will operate on reduced or alternating schedules (“interlocking”).
“The health and safety of students and staff is our top priority. Construction work at more than 86% of schools is now complete. However, at campuses where we have identified pending issues, we have postponed faculty arrival and enrollment to ensure that work is completed properly without putting students and staff at risk. These measures have been discussed with communities and the Teachers Association. All of this is in response to our commitment to the ongoing improvement of school infrastructure,” Raices Vega said in a press release.
The secretary stressed that no school will operate in virtual mode, but rather they will adjust their schedules to operate in person starting August 19. In these 30 schools, work is still being done such as repairing short columns, painting and sealing roofs.
The new school year began last Thursday, with the arrival of staff at the campuses, while classes begin on Tuesday, August 13.
Last year, Education, the Infrastructure Financing Authority (AFI) and the Public Buildings Authority (AEP) announced the investment of $3.5 billion over five years to advance hundreds of projects to correct infrastructure problems in the country’s 856 public schools, including repairs to short columns – which began in 2021 –, sealing roofs, repairing windows and rebuilding 41 schools.
Schools in the San Juan and Bayamon regions were the latest to be impacted by the project to repair short columns, an element of the school design that makes them more susceptible to damage in the event of an earthquake, Raices Vega said.
In total, short column work has already been completed in 477 schools, Raices Vega said. The work is due to be completed by December this year, he said.
The secretary also said that sealing work on roofs in 380 schools has already been completed and 811 schools have already been painted inside and out.