Arguing that this is a necessary investment to essentially eliminate load shifting due to a shortage of electricity production, Generate PR formally requested the Energy Bureau (NEPR) authorization to rent temporary units with the capacity to generate up to 565 megawatts (MW) for two years.
Although it requested permission from NEPR to open a bidding process, Genera PR acknowledged –in a motion last Friday– that It is unknown what the source of financing would be for the rental of the units.
The operating model of the equipment – which would burn natural gas, with diesel as an alternative fuel – explained the private administrator, would be similar to that used for the 17 units that the government rented through the Federal Emergency Management Agency (FEMA) until March, when the Electric Power Authority (AEE) purchased 14 of the generators. FEMA, in addition to financing 90% of the rental, covered the same amount of the purchase.
According to Genera PR, additional generation is necessary at least until 2026, when several pending projects are projected to be completed.such as the installation of energy storage batteries in the power plants and rapid response units, which remain in limbo due to differences between the company and the NEPR over the number of machines to be purchased.
“The implementation of these projects will take time,” Genera said in the motion. “Therefore, Genera PR respectfully requests the NEPR to order the initiation of a critical requisition process to improve the stability and reliability of Puerto Rico’s electrical system by facilitating the expeditious integration of approximately 565 MW on a temporary basis.”
If the request is approved, Genera PR estimates that the generating fleet will have an installed capacity of 5,500 MW, of which up to 3,300 MW would be used to cover peak demand, another 1,060 MW would remain in reserve and 1,140 MW would be in rotating maintenance.
The tender, Genera added, would require bidders to “oversee delivery of units to all locations, facilitate construction, installation and operation (excluding environmental permits), connect the units to the grid in coordination with the transmission and distribution operator, commission the units and undertake decommissioning, demolition and demobilization upon expiration of the lease.”
“Efforts are underway to secure the funds needed to cover rent for two years, with tariff financing as a last resort. However, the bidding process must begin and be conducted in parallel with the identification of potential sources of financing,” Genera proposed.
The private operator presented its proposal within the framework of the evaluation of the “priority plans” that the NEPR ordered to be developed Generates PR, LUMA Energy and the AEE after the massive blackout on June 12. The plans, as ordered by the Bureau, must contain initiatives that can be implemented within two years.
According to one of the appendices to the motion, Genera intends to install 260 MW at the Aguirre plant in Salinas and another 100 MW at the San Juan plant. At the Costa Sur (Guayanilla), Jobos (Guayama) and Yabucoa plants, units with a capacity of 55 MW would be installed, and at Cambalache (Arecibo), another 40 MW.
Through a contract with the AEE signed in March, New Fortress Energy –Genera PR’s parent company– can supply natural gas to all of these generating facilities until 2028.
From a technical standpoint, Genera PR justified the motion based on a “load loss expectation” (LOLE) analysis that LUMA Energy presented in December 2023. In that report, LUMA calculated that, based on the existing generation capacity – not including the 14 units acquired in March – Puerto Rico could suffer deficiencies for an average of 37.5 days per year.
By incorporating the units purchased a few months ago into the calculation, the LOLE is reduced to 18.5, Genera stressed, and the indicator would reach 0.1 days if the 565 MW requested are allowed to be added, in line with the standards of the North American Electric Reliability Corporation.
Negotiation establishes calendar
While, in a resolution and order –also dated last Friday–, the NEPR set the schedule for passing judgment on the plans submitted by LUMA, Genera and the AEE in July.
On September 11, the three parties will have to participate in a technical hearing together with other “interested parties”, while, by the 25th of that month, the public corporation and the two operators will have to respond to any additional requirements from the regulatory body.
“During the virtual technical hearing, LUMA, Genera and AEE will present and discuss in depth their preliminary plans. Representatives of each company and their consultants should be prepared to answer questions from the NEPR, its staff and consultants, regarding their presentations and all aspects of the plans.“, the entity indicated in the resolution.
On October 2, the NEPR will hold a hearing to hear public comments, and the public will also have until October 8 to submit written comments.