Although only two mayors had formally notified LUMA Energy In addition to their intention to intervene with the electrical system in their respective municipalities, several additional municipal executives acknowledged that, if they did not see progress in restoring the service, they would still resort to hiring brigades to carry out work aimed at re-energizing it.
On Saturday, at 4:00 pm, 91.7% of customers, in general, had electric service, but several mayors denounced The New Daythat, in their towns, there are still many so-called “pockets” without power and that they do not perceive sufficient movement from the private operator to speed up the restoration in those areas, affected since the Tropical Storm Ernesto passed northeast of the archipelago between Tuesday and Wednesday.
According to LUMA data, the number of customers without power amounted to 122,507, and the majority of them – 44,263 – were concentrated in the Carolina region.
Elliot Colon Whitemayor of Barranquitas, and Jesus Colon Berlingeriits counterpart from Orocovis, commented to this newspaper, separately, that they already had brigades ready to begin carrying out different tasks between Saturday and Sunday, despite the objections of LUMA, which has stated that uncoordinated work could lead to a destabilization of the system and, in the worst case, a tragedy..
The day before, at a press conference, LUMA stated that the mayors of Isabela, Miguel “Ricky” Mendezand San Lorenzo, Jaime Alveriothey had informed him that they would intervene in the electrical system, an action that is permitted under the Municipal Codeprovided that a state of emergency has been declared and the city council notifies the operator five days prior to the start of work.
Under these circumstances, municipalities will be able to “carry out all necessary steps and work to normalize or restore the electric power system, as well as the facilities for the supply and treatment of water and wastewater.”
The press office of LUMA, which has said it has more than 1,500 employees in the field, said Saturday it had not received any additional notifications.
“We saw that LUMA began to work with some brigades and began to energize several areas, but, As the days go by, we have observed that the movement is not what we need.. We are aware that LUMA apparently does not have the capacity in terms of brigades, of personnel. The personnel that is working is very good, the same one that had the Electric Power Authority (PREPA)but they have fewer personnel,” said Colon Blanco, who said he plans to activate private brigades on Sunday if he does not see improvement.
“There are many areas, which are the famous pockets, where they come and energize the largest, but the small pockets are left without power. Sometimes, it is a ‘machete’ that is left down, a cable that fell, well, that is fixed and, when they energize the area, everything is fixed,” added the mayor of Barranquitas, stating that, on Friday, LUMA personnel prevented the private brigades from intervening.
The New Progressive Party executive, however, stressed that it will insist on the activation of the brigades, even if there has not been an official notification to LUMA and the statutory term of five days has not passed.
“I will notify them and do it, unless between now and tomorrow (Sunday) they perform a miracle and turn on 95% of the town,” said the mayor, estimating that, at present, the proportion of customers with service in Barranquitas is around 65%.
Isabela Mayor Mendez said that, in his case, after having notified LUMA on Thursday, he could order actions between Monday and Tuesday. The municipal executive, who faced a complaint from LUMA after the Hurricane Fiona in 2022, when he announced that he would activate brigades to restore the serviceestimated that between 25% and 30% of the population lacks electricity.
“Our brigade can work on replacing secondary lines, replacing blown machetes or fuses, and defective fittings that need to be fixed. They are private contractors who worked for the AEE and are retired. It is a small group of approximately five people.“, said the Popular Party mayor. “The problem with LUMA is that it has few staff, and the staff has little knowledge of the locations of breakdowns, which are always typical in the same places.”
The mayor of Orocovis, for his part, pointed out that the pockets are concentrated in the “periphery” of the urban area, even affecting several businesses in the town. According to Colon Berlingeri, the five-day term provided by the Municipal Code expires this weekend, since he has maintained continuous communication with LUMA since Ernesto’s passage.
Colon Berlingeri, from New Progressive PartyHe added that he would probably activate the brigades from Saturday afternoon.
“I’m going into the pockets. That’s what I’m going to focus on, to restore service,” he said, estimating that half of the town is without power. “They put obstacles in the way when you try to do this kind of thing, but I have no choice. My people are in need of light. There are people who have physical needs, and they have to be addressed.”he stressed.
On Saturday, it was not possible to get hold of Alverio, the mayor of San Lorenzo, for an interview.