The consortium LUMA Energy sent a letter this Sunday to the mayor of Orocovis, Jesus “Gardy” Colon Berlingeri, in which he requested that he “cease and desist” from using municipal brigades to carry out electrical repair work in the town because, allegedly, his order not only violates provisions of the Municipal Code, but also “puts at risk any person who, under his instructions as mayor, works in the transmission and distribution system (of energy) without authorization and prior coordination with LUMA.
Colon Berlingeri made, yesterday, Saturday, a publication on your Facebook accountin which he indicated that municipal brigades were continuing with the work of repairing the electrical lines in various neighborhoods and sectors of Orocovis. The letter sent this morning was sent by Angel Rotger SabatHead of Legal Affairs of the consortium.
“LUMA shares your desire to restore power to your municipality in the shortest time possible, and is actively working to achieve that goal. Please be assured that LUMA has the resources necessary to complete restoration efforts safely and in accordance with industry standards,” Rotger Sabat said in the letter.
“We are very concerned about the images we have seen posted by the Mayor of Orocovis on social media of people working on power lines in his municipality without authorization and without the proper safety equipment, which represents an immediate danger to the people of Orocovis and to our employees.”LUMA added in a written statement.
Rotger Sabat detailed that Colon Berlingeri met yesterday, Saturday with Ishvara PaniaguaKey Accounts representative, and with Kermith CarrionKey Account Manager, on recovery efforts following the passage of Tropical Storm Ernesto.
“However, hours later, LUMA learned, through a communication on social media, that the municipality had activated its brigades to intervene with the electrical lines to restore service. As a result of this, Mr. Carrion contacted you again to confirm the work plans. In said call, Mr. Carrion indicated that that day (Saturday) the LUMA brigades would be working in various sectors of Orocovis, including the communication antennas of the Maravilla neighborhood, the broken breaker in feeder 9901-02 (and that 20% of it would be energized), repairing the primary lines of the Damian Abajo, Culebra, Saltos Coli neighborhoods, part of the Gato neighborhood and the PR-155 highway,” said Rotger Sabat.
The LUMA official highlighted that the consortium confirmed to Colon Berlingeri that employees of the consortium would work in sectors identified by the mayor on a list and that he was told that “he should not work on the electrical system, as he had proposed, to avoid accidents with our brigades and the citizens, or compromise the system, to which you (Colon Berlingeri) agreed. and indicated that he would remove the groups that were working on the lines to allow LUMA to work.”
However, Rotger Sabat indicated that, in light of the activation of the municipal brigades, LUMA made the decision to withdraw its employees from the work planned in Orocovis “due to the risk to the safety of the LUMA brigades caused by the work of the municipal contractors.”
Rotger Sabat denied that LUMA received a letter that Colon Berlingeri allegedly sent on August 17, 2024, notifying about the activation of municipal brigades to repair the electrical lines (as provided for in Article 1.018(v) of the Municipal Code). Therefore, the consortium cannot guarantee that the repairs carried out by the contractors meet industry standards, nor can it guarantee that the work qualifies for reimbursements from the Federal Emergency Management Agency (FEMA).
The private company said it was working to restore service as soon as possible but that this work must be done “correctly and safely to protect the public and all of our customers.”
“We cannot stress enough that work on the transmission and distribution system is, and must be, completed by trained and skilled personnel. In addition, all industry standards and applicable laws must be followed, in addition to coordination with LUMA, to ensure the safety of our customers and our teams.”read the statements.
The New Day He requested a reaction from Colon Berlingeri and is awaiting a response.
Colon Berlingeri is not the only mayor who expressed intentions to activate own brigades for service restoration in their villages. In Barranquitasits counterpart, Elliot Colon Whitealso reported that he had crews ready to work on the lines that supply his municipality.
Only two mayors, Miguel “Ricky” Mendez in Isabella and Jaime Alverio in Saint Lawrencenotified LUMA that they would carry out work under the Municipal Code, which establishes that these actions are legal as long as there is a declared state of emergency and the city council notifies the operator five days in advance of the start of work.