He Energy Bureau (NEPR) partially approved the extension requested LUMA Energy to deliver the review of the Integrated Resource Plan (PIR) for the electricity grid, a document that should have been ready by June 28, when the consortium asked that the deadline be postponed until May 2025.
As part of its resolution and order –issued on Tuesday–, the NEPR gave way to a “hybrid schedule” in which LUMA must submit part of the necessary documentation by November 29 and the rest by February 28, 2025..
Despite the Failure to comply with the June 28 deadlinethe NEPR did not issue any fines or penalties against LUMA, which notified the regulatory body that it would not be able to comply with the term just three weeks earlier.
“LUMA’s request to extend the delivery date of the (PIR) does not directly address the immediacy or severity of Puerto Rico’s current operational situation. The frequency of load shedding events, 111 in the past year, is an unacceptable and immediate reliability issue,” the NEPR stated in the resolution.
“While the purpose of the IRP is not to deploy emergency resources to eliminate operational problems, there is an immediate need for an updated resource plan, especially one that includes capacity resources with near-term deployment dates as well as longer-term plans for an economically optimized capacity and energy resource base aligned with public policy,” the agency added.
In explaining its reasons for failing to meet the June 28 deadline – a date that represented a postponement from the original March 28 deadline – LUMA stated that its technical consultant, the firm Black & Veatchhad faced problems with the software used to model future scenarios for the electricity system. LUMA also argued that if it delivers the revised PIR on or before May 16, 2025 – as proposed to the NEPR – it would be within the 20-month period since it engaged Black & Veatch, which it said falls within industry standards.
Instead, in the resolution and order, The NEPR established that, by November 29 of this year, LUMA must submit the 10 scenarios that would be evaluated once the PIR enters its adjudication phase, in which the public and interested parties will be able to intervene.Scenarios should include those energy generation resources that will be available in the future, as well as possible schedules for the decommissioning of existing units.
In this regard, the scenarios must consider the statutory transition to renewable energy, which includes the goal of reaching a 40% portfolio by 2025, which is presumed to be impossible to meet given the delay in the development of large-scale clean generation projects.
By February 28, 2025, the grid operator must deliver the remaining components of the PIR, which includes the analysis of the necessary investments in the transmission and distribution system.part of which is included in federally funded reconstruction projects.
Although it granted until next year to submit the transmission and distribution analysis, the NEPR “expects LUMA to provide, at a minimum, a qualitative descriptive summary of how it anticipates that the planned transmission facilities will support its preferred resource plan when it delivers the resource plan development components on November 29, 2024,” the agency said.