More than a year and a half after being closed for repairs, the emblematic Naranjito cable-stayed bridge The highway will reopen its four lanes on Monday, after an investment of $33 million, which is added to the original cost of the structure, which was inaugurated late in October 2008.
In an exclusive interview with The New Daythe executive director of the Highways and Transport Authority (ACT), Edwin Gonzalez Montalvoassured that, unlike what happened when the bridge was inaugurated, this time the structural works have been completed and certified by the Federal Highway Administration (FHWA, in English).
“At no time have I received a call from the governor (Pedro Pierluisi) or any politician that the work has to be moved forward or done faster; they have given us the necessary space at all times to do the required studies and open the bridge when it is ready, and it is ready now,” Gonzalez Montalvo stressed.
The bridge was closed on January 30 to begin repairs, affecting thousands of residents in Naranjito, Barranquitas, Comerio, Morovis and Toa Alta who frequently cross the structure. According to ACT data, the average daily traffic on the bridge is 14,000 vehicles.
1 / 14 | Photos: the turbulent construction of the Naranjito cable-stayed bridge. Construction of the Naranjito cable-stayed bridge began on August 2, 2002 and consisted of the construction of 0.71 kilometers of road with two 3.65-meter lanes, a walkway in each direction, and a 320-meter cable-stayed bridge on 82-meter beams. (Xavier J. Araujo/2005) – Xavier J. Araujo
In January of last year, a This newspaper’s investigation revealed irregularities and construction defects in the bridge and it was closed. Two and a half months after closing it, the ACT opened a reversible lane on April 18, after studies concluded that the measure was viable while repairs continued, with the aim of serving vehicular traffic during the morning and afternoon rush hours.
Then, in December 2023, the ACT opened two repaired lanes to traffic, one in each direction, while work continued on the other two lanes and the cables. Gonzalez Montalvo indicated that the work was originally scheduled to be completed in July, but that the completion of studies and operations, while one or two repaired lanes were already open, delayed the work by a month.
However, he said the reopening – which will take place during an official event on Monday – is within the planned time frame of summer 2024.
The cost of the repairs and related maintenance amounted to $33 million, about $7 million more than originally estimated. This amount is in addition to the $31.8 million that the bridge originally cost to build.
“The completion of the improvements to the cable-stayed bridge in Naranjito is a great achievement of our administration, which joins a wide range of bridge and highway projects throughout Puerto Rico. This is a project that since 2008 had obvious defects in its construction that caused undulations in the bridge slab, so that only one lane could be used in each direction,” Pierluisi stated in written statements to this media.
“Today, it is a reality that all people who travel through the area can use the repaired and safe bridge,” said the governor.
Construction of the cable-stayed bridge began in August 2002 and was inaugurated on October 24, 2008 by Governor Anibal Acevedo Vilaeleven days before the general elections of that year, after the ACT and the contractor Las Piedras Construction agreed to speed up the work. From the moment it was inaugurated, the surface or slab of the bridge showed serious undulations that constituted the main fault, pointed out in various inspections and studies at various times after the inauguration. The situation caused the ACT to permanently close two lanes in May 2014.
At the beginning of last October, ACT began to carry out one of the main phases of the repair: the placement of the filler – polymeric material – on the rails, eliminating the undulations that represented a construction and safety problem since its inauguration. The repairs were carried out by the company Ferrovial, while the subcontractor Freyssinet was in charge of the maintenance corresponding to the cables and boots of the bridge.
The mayor of Naranjito is pleased
The mayor of Naranjito, Orlando Ortiz Chevresnoted that it took four government administrations before an issue that had affected residents of this central part of the country for years was finally addressed.
“We have been working hard to achieve what we have been working on since 2009. We are very happy and very grateful because now we will have four lanes working and this will undoubtedly improve the quality of life of people and the stability of traffic on this very important road,” the municipal executive stated in an interview with this media.
Without assigning responsibility for failures
On the other hand, although the ACT celebrates the completion of the repairs and reopening of the bridge, The CEO acknowledged that no responsibility has yet been assigned for the structural failures. Following the publication of this media’s investigation, the Office of the Comptroller of Puerto Rico and the Department of Justice They launched an investigation that is still ongoing.
“We have provided them with all the information we have at hand,” said Gonzalez Montalvo. The official added that, once the work is completed, the ACT will submit a final report to both entities “so that they can take the necessary measures.”
“We are talking about all the studies that were carried out, load studies, analysis of the bridge, the chronology of the construction process, surveying, details, all the data, which can be compared with the original plans,” he said.
With repairs completed and maintenance performed, the bridge is back to the 50-year or more resilience it was designed for, the engineer said. The extension of this period is tied to the structure receiving the corresponding maintenance, when necessary, in the coming decades, something that also did not occur after the inauguration.
The executive director of the ACT acknowledged the work of engineer Ramon Carrasquillo as a key figure in the repairs. Carrasquillo, who collaborated with this newspaper during the investigation into the bridge failures, died suddenly in February of this year.