He Puerto Rico Energy Bureau (NEPR) gave the go-ahead to a group of three projects renewable energy large-scale projects awarded in recent months that would add 60 megawatts (MW) of photovoltaic production capacity and another 60 MW of electrical storage, which represent a small part of the volume anticipated for the second stage of the acquisition provided for in the current Integrated Resource Plan (PIR).
The resolution and order The NEPR says that one of the solar projects would have the capacity to produce 20 MW and a second, 40 MW. The third project would be an independent battery storage project, which could deliver 60 MW for four hours.
The document, released on Monday, does not specify the identities of the winning companies, since the contracts are still awaiting approval from the Fiscal Oversight Board (JSF). The agreements were already approved the Governing Board of the Electric Power Authority (AEE) and the endorsement of the NEPR was required to validate that the projects are aligned with the public energy policy.
“The AEE is warned not to execute the contracts until it obtains the approval of the JSF, since, without it, they could be declared null and void.”the NEPR indicated in the resolution,
Clean energy tranches were the mechanism included in the PIR approved in 2020 to steer the country towards the statutory energy goals, which stipulate that, by next year, a portfolio of 40% renewable sources must be achieved. In 2023, when adding the energy from large-scale projects to that contributed to the network by target metering clients, the figure barely exceeded 5%.
In total, the six stipulated “tranches” were to result in the acquisition of 3,750 MW of energy and 1,500 of storage, which is estimated to have been sufficient for Puerto Rico to achieve the goal of 40% by 2025.
According to the PIR, through the second “tranche”, recently awarded, up to 500 MW of production capacity and another 250 MW of storage were to be contracted, so The totals awarded were just a fraction of the targetIn the resolution and order, the NEPR did not elaborate on the obstacles faced in achieving the minimums established in the PIR, nor how many offers were received.
“Particular attention was paid to the reasonableness of the proposed prices, ensuring that they were competitive and aligned with industry standards”the agency said.
In the first tranche – which also fell short of contracting targets – agreements were finalised to add around 600 MW of solar power and 350 MW of storage.
The tranches have also fallen substantially behind the schedule outlined by the PREB, which called for the final RFP to be issued in the summer of 2023. At the conclusion of the first tranche—which was administered by PREPA—in 2022, the regulator appointed an independent contractor to process the proposals for each round and submit a report to a selection committee, comprised of representatives from several agencies, that awards the bids.
The second section, therefore, was the first to follow the alternative procedure established by the NEPR.
In an interview with The New Day In April, NEPR President, Edison Aviles, left the door open to modifying the renewable energy purchasing process through the review of the PIR, a document that must be delivered to LUMA Energybut which, after several extensions, will not be evaluated until next year.
Resolution and order from the NEPR, August 26