Delays and cost increases in the execution of the project to replace the fleet of emergency generating units led to the Puerto Rico Energy Bureau (NEPR) to conclude that GeneraPR “may have made false representations of material facts” to convince the entity that the procedure for acquiring the machinery should be modified with respect to the process that the Electric Power Authority (AEE) had been in place prior to the transition between the two companies.
GeneraPR, which took over the country’s electricity generation in July 2023, must show cause, on or before September 5, why he should not be fined $25,000 Given the obstacles it has faced in acquiring the new units, the NEPR determined in a resolution and order dated Wednesday.
Immediately, the spokesperson for GeneraPR, Ivan Baezwas not available to comment on the NEPR guideline.
As reported by El Nuevo Dia last Mondaythe estimated costs of acquiring and installing the so-called peaking units – necessary to avoid load shifting when there is an increase in demand or when the main plants break down – have increased from $800 million to $911 million, while their entry into operation, initially projected for the end of 2025, has been postponed until at least 2027, according to a recent report of the operating company itself.
In Wednesday’s resolution, the PREB noted that PREPA had planned to award its request for proposals (RFP) on July 31, 2023, one month after the transition to GeneraPR materialized. The private company, however, received authorization from the PREB to restart the RFP, under the premise that it could achieve “significant savings and a reduction of 9 to 12 months in execution time.”
The AEE RFP contemplated that the 11 units it hoped to purchase would enter into service two years after the award, that is, in mid-2025.
“PREB determines that there is sufficient cause to believe that Genera may have made false representations of material facts regarding projected savings and commercial operation date, potentially misleading PREB into authorizing the continuation of its proposed proceeding.”the regulatory body indicated in the resolution and order.
“As such, PREB orders Genera to show cause why it should not be assessed a $25,000 fine for the misrepresentation regarding the RFP process,” the order added.
Specifically, GeneraPR must respond to the grounds for promising savings in time and money, a “detailed explanation” of the reasons for the “discrepancies” between estimates, “circumstances or evidence” that mitigate the failure to meet expectations, and clarify whether part of the increase in costs would be covered by federal funds or some other source.
The NEPR resolution and order states that, according to PREPA’s RFP, the purchase of peak units was estimated at $613.5 million.
In written statements sent earlier this week, Baez argued that The AEE calculations had not taken into account “the post-award negotiation of the terms and conditions of the contracts or the delivery times of the equipment”.
The increase in GeneraPR’s projected costs comes despite the fact that, in recent weeks, the NEPR only authorized it to purchase up to 10 units with a combined capacity of 244 megawatts (MW), instead of the 394 MW that the company intended to acquire. PREPA had planned to acquire 11 units with a capacity of no more than 281 MW.
On Tuesday, the CEO of the Central Office for Recovery, Reconstruction and Resilience (COR3, in English), Manuel Laboysaid that, in part, the changes in the procedure responded to the financing mechanism selected for the purchase.
Months before GeneraPR took over control of the fleet, the Federal Emergency Management Agency issued a directive estimating the cost of mitigation works it would finance for the electrical system at $7.6 billion, regardless of the source of the funds.
Following this notification, COR3 pushed for the majority of the power grid projects – including the purchase of peak units – to be transferred from the section 404 –which has a cap of $4 billion for all Puerto Rican government entities– to 406 of the Stafford Act, in order to maintain greater flexibility for other agencies.
Under Section 406, the government – in this case, PREPA – must contribute a 10% match to the cost of the works.
Resolution and order from the NEPR, August 28