Just days after notifying GeneraPR which was exposed to penalties for alleged “false representations” regarding a project to purchase generation units, the Puerto Rico Energy Bureau (NEPR) again demanded that the company show cause why it should not be fined after canceling, in the last two weeks, three scheduled inspection visits that personnel from the regulatory body tried to make to the San Juan plant.
The NEPR stated, in the most recent resolution and orderthat “last-minute” cancellations “are not an isolated incident, but part of a deeply worrying pattern that reflects a systemic disdain for regulatory authority.”
“This recurring behavior is unacceptable and poses a severe threat to the integrity of the regulatory framework established to safeguard the provision of safe, reliable and affordable electric service for the people of Puerto Rico.”the entity stressed in the document issued on Friday, which was initially disclosed by the commentator Jay Fonseca.
In total, GeneraPR faces three fines of $25,000 each for the cancellations corresponding to August 19, 20, and 26, for a total of $75,000. The NEPR gave the generating fleet operator until September 5 to show cause as to why a penalty of that amount should not be imposed, which represents the daily limit that the agency can apply against electric companies.
According to the NEPR, on August 26, its representatives were granted access “only after insistence.”
In response to a request for reaction from The New DayGeneraPR spokesperson, Ivan Baezdescribed the controversy on Saturday as “a matter of coordination and communication. I understand that there has already been talk with the NEPR to establish a mechanism for coordinating visits.”
“On one of the last occasions (August 26), we were working on an emergency, because we had received damage to the units, and we had the team focused on the emergency,” said the operator’s vice president of Public Affairs, who added that It is important that the NEPR can carry out its inspections so that it can “see the work” and assess the needs faced by the generating facilities..
In the interview, Baez was unable to specify the reason for the two previous cancellations, but insisted that, normally, a long notice period is not required to coordinate the inspection. “If there are emergency situations, it is important to provide communication so that work can be done, because the operations team was immersed in the repairs,” he said.
In the particular case of the San Juan plant, it has been operating with limited capacity for several weeks, with unit #6, one of the two main plants of the facility, out of service.
It was not immediately possible to validate with the NEPR whether a method had in fact been established to guarantee future access to the generating plants.
NEPR “has not received an explanation”
In the resolution and order, however, The NEPR was emphatic that it has the authority under the law to conduct “announced or unannounced” inspections at its sole discretion.According to the agency, the cancellations of the visits, on all three occasions, occurred when the team of advisors was already at the security checkpoint of the plant.
“Despite the seriousness of this situation, NEPR has not received a satisfactory explanation from Genera for this pattern of cancellations and apparent resistance to facilitating regulatory oversight activities.”adds the resolution, signed by the five commissioners of the entity, which speculates that the incidents respond to “the absence of effective protocols” or a “voluntary disregard” of its powers.
In the document, the NEPR also asserted that the company’s actions “could be considered a criminal offense, potentially exposing her to legal consequences for obstructing regulatory processes and limiting the duties of the PREB.”
According to the regulatory body, GeneraPR must designate “separate personnel” to handle visits “regardless of any ongoing emergency.”
Baez, on the other hand, said that no additional personnel is required.
“Not at all. It was more a matter of coordination and timing because we were in the middle of an emergency,” he stressed, acknowledging the NEPR’s authority to carry out field inspections.
Last Wednesday, the NEPR issued a resolution and order stating that due to delays and cost increases in the project to purchase backup generation units, GeneraPR was subject to a $25,000 penalty. In this case, it is a project, funded with federal funds, that was supposed to result in the installation of 10 units by 2025, at an initially estimated cost of $800 million, but which, according to the operator, will now take until 2027 and will require more than $911 million.
Resolution and order of the NEPR, August 30.