The executive director of the Electric Power Authority (EEA), Joshua Columbusexpressed serious doubts about the possibility of the purchase of the three generation units whose auction the public corporation has been pending since July, due to the lack of guarantees for the financing of toxic emissions control equipment.
According to Columbus, the Federal Emergency Management Agency (FEMA, in English) refused to authorize funds for the acquisition of emissions control equipment, the cost of which GeneraPR –the fleet manager– estimated the cost at $150 million. The equipment would be used not only to regulate emissions from the three units that the AEE plans to acquire soon, but also from the 14 generators it purchased in March and have been in service since then at the San Juan and Palo Seco plants.
For the purchase of the three portable generators – which would produce around 100 megawatts (MW) – the AEE has available $65.7 million allocated by FEMA since last March, an amount that Colon assured is sufficient to complete the transaction. However, according to the official, FEMA reversed its initial commitment to also finance the acquisition of emissions controls..
“Recently, they modified that language and said there is no possibility of additional funds to the PW (project sheet) to cover those needs, and This has caused us not to award the RFP (request for proposals), which is already ready to be awarded.”Colon said at a press conference on Wednesday.
FEMA did not immediately respond to Colon’s remarks.
Between the summer of 2023 and March of this year, the generation fleet had 17 portable generators available, adding up to 350 MW of capacity to the system. However, in March, only 14 of the machines could be purchased, so efforts have continued to acquire another three.
At a time when the country is immersed in an extended streak of blackouts due to deficiencies in power generation, Colon said that FEMA should extend the authorization for the use of emergency units for at least five years.When allocating funds for the purchase of the 17 generators, FEMA included a condition that they not be used after December 31, 2025.
For Colon, this condition is incompatible with the requirement to implement environmental controls due to the time required to install this equipment.
“The manufacturers (of the emissions control equipment) have said that manufacturing and placing them in Puerto Rico would take between one year and 18 months, at least. Therefore, if that agreement were reached today, and those (purchase) orders were placed, that equipment would arrive at the end of the mission, which is in December 2025. That would make the effort unreasonable from the point of view of the return on investment being made. These are issues that need to be addressed.. What we want is for the mission to be extended, (because) we understand that the mission of the units continues to be as necessary as it was originally, and that it should be extended for five additional years,” said Colon, who stressed that the generation units could enter into service two months after their purchase.
According to the engineer, the Federal Environmental Protection Agency The US has indicated that it will notify the emissions standards that will apply to portable generators before the end of the year. Since the last decade, the air basin of the Palo Seco and San Juan power plants has been is designated as an air quality non-attainment zone.