The installation of a new transformer at the Useras substation, in Saint Elizabeth –which has been out of service for more than three months–, will take about five additional weeks, it was revealed this Friday in a public hearing of the Commission for the Oversight of the South-Central Region of the House of Representatives.
According to the press release of the President of the Commission, Star Martinez Sotoofficers of LUMA Energy They indicated that the contract for the transfer of the team would be signed today, at a cost that would fluctuate between $300,000 and $400,000.
At a previous hearing, held on July 23, LUMA had estimated that, once the transfer began, It would take about five weeks to complete the processes to get the transformer into service..
In June, the transfer by sea and land of another equipment, from the Buen Pastor substation, in Caguas, It cost almost $4 million. That transformer, however, failed in the final phase of testing and had to be discarded.
According to the company in charge of the energy transmission and distribution system, August 30 was the last day for companies to submit their quotes for the transportation of the transformer and, last Tuesday, the purchasing and acquisitions team met to select the best option. The signing of the contract, according to the director of External Affairs of LUMA, Jose Perez Velezwould occur this Friday.
On the other hand, Perez Velez maintained, in the public hearing –held in a restaurant in Santa Isabel–, that LUMA still does not have a quote for the repair of the damaged transformer that was transported at a cost of $4 million.
“EFACEC, the company that manufactured the damaged transformer located at the Useras substation in Santa Isabel, has not yet submitted its quote to repair the equipment on the island. We hope that the company will submit it next week,” said the executive of the consortium.
The failure of the substation’s original transformer was recorded on June 1 and, since then, Santa Isabel customers, Coamo and Aibonito have experienced service instability. In response, LUMA carried out work to increase the capacity of transmission line 4800, which runs between Cayey and Santa Isabel, installed temporary generators and began work to rehabilitate transmission lines 100 and 200, which connect Useras to the Costa Sur power plants in Guayanilla and Aguirre in Salinas.
Martinez Soto, representative for district 27, insisted that the legislative body will continue to monitor LUMA’s work in the region.
“Thanks to the oversight work we have carried out in these public hearings, together with the district mayors and senators, We managed to get these jobs prioritized, and we will soon have lines 100 and 200 up and running.″, said the popular representative.