EcoElectrica units return to service after halting operations by order of LUMA Energy

EcoElectrica units return to service after halting operations by order of LUMA Energy

Two of the three generating units of the plant EcoElectricin Penuelas, returned to service in the early hours of this Saturday after receiving authorization from LUMA Energywhich the day before ordered the plants to be shut down due to apparent problems with the transmission lines that connect to the cogeneration plant.

“We wish to inform that, after the interconnection works with the electrical grid were completed, the CT1 and STG units of EcoElectrica have returned to service in the early hours of the morning.. Our team will continue to work continuously to ensure the full normalization of our operations over the coming days,” the company said in writing.

According to the portal of GeneraPRAt 10:30 am on Saturday, one of EcoElectrica’s combustion turbines (CT1) was producing 171 megawatts (MW), while the combined steam cycle (STG) was contributing 107 MW, for a total of 278 MW.

The cogenerator’s second combustion turbine – which began the annual maintenance programme for its three units on 1 September – remains offline. At maximum capacity, EcoElectrica’s three units generate up to 540 MW.