As part of the evaluation to develop a “priority plan” that achieves stabilization of the power grid Over a period of two years, the Puerto Rico Energy Bureau (NEPR) questioned the proposal of GeneraPR to lease additional generating units that would add up to 565 megawatts (MW) of capacity on a temporary basis, citing concerns about the time it would take to execute such a project.
In view of Genera’s proposals to give way to the initiative would guarantee the country sufficient electricity production to eliminate load shifting As those who have plagued the population almost daily for the past month, the president of the NEPR, Edison Avilescast doubt on the ability to carry out the initiative before the generating fleet operator develops other ongoing projects, such as the installation of storage batteries or the replacement of essential components in the plants, which would improve the performance of the permanent units.
These projects, for which Genera has federal allocations, should begin to produce results between late 2025 and 2026.
“There is talk of providing transition generation, connecting it as if they were ‘trailers’ at certain points, because they understand that, to achieve that, they are going to execute more or less in the same way that the Corps of Engineers (of the Army, or USACE, in English), which obtained the permits and all the scaffolding, which as a country we have not achieved in 20 years, in six to eight months,” said Aviles, in reference to the installation of megagenerators led by the federal government, in 2023, to add 350 MW to the generating fleet after the Hurricane Fiona.
In March of this year, the Electric Power Authority (AEE) purchased 14 of the 17 generators that, until then, USACE operated through an agreement with the Federal Emergency Management Agency (FEMA), which are located in the Palo Seco (Toa Baja) and San Juan power plants.
“The execution time is key because, if we are going to take the same time, from two and a half to three years, which is what the batteries and the renewable energythen the proposal would not make sense. We have to be sure that we will have that connected in a very short time,” Aviles stressed during the presentation of Genera.
Genera’s chief regulatory officer, Katiuska Bolanosreplied that “the big difference” with respect to other projects that have been delayed – such as the purchase of permanent backup generation units – “is the issue of availability.”
“If we use other alternatives like the one used by USACE at that time, which went to the market and identified that the most viable solution was units that had already been previously used and were already available, without waiting for them to be built, then it was the fastest solution,” Bolanos said.
In his presentation to the NEPRGenera stressed that there is “openness” at the level of the Executive and the Congress federal government to financially assist Puerto Rico in acquiring greater electricity generation capacity.
“We believe that if we unite, we can be ‘advocates’, (advocate for) different initiatives to achieve these goals”Bolanos said, mentioning that there is a bill before Congress that contemplates exploring strategies to address the deficiencies of the generation system in Puerto Rico.
Genera’s Vice President of Operations, Daniel Hernandez Moralesbrought up in the technical hearing the The company’s “concern” with the dispatch demands that LUMA Energy is making with several of the main base units of the systemnoting that the constant increases and reductions in generation that have been requested have contributed to the repeated breakdowns of the past few weeks.
“At night, you can’t get one more megawatt out of the units, and during the day they are below the operational minimum,” said the engineer.
Jorge Camachoone of the NEPR consultants, then questioned whether Genera is adequately supervising the repair work commissioned to contractors, expressing concern about the continued breakdowns in components of the generating units, such as boilers.
“You are starting from a false premise, that the machine has a fault and it was a fault, for example, in the same place as a boiler. What happens is that when you take a machine out (for repair), you do the repair and you put it into service – and hydrostatic tests are always done – it can happen that another section of the boiler breaks. It is not that the work was faulty.“said Genera’s head of operations.
A challenge to repair substations
The presentation and discussion of Genera’s plan took place after LUMA highlighted, in his two-year proposalurgent attention to work in several substations with a high probability of suffering critical failures, as had been anticipated in a draft submitted to the NEPR, where it identified 11 vulnerable transformers in these facilities.
According to LUMA, one of the difficulties in carrying out this task is the need to standardize the models of transformers used, so that, in the future, it will be possible to have spare parts in inventory, instead of depending on purchase orders with long delivery times.
LUMA also referred to the initiative to clear vegetation from power lines, stating that, So far, it is subdivided into 42 projects to be submitted to FEMA, of which only one has been approved.. Camacho then mentioned that when LUMA came into operation in 2021, it estimated that vegetation clearing would be completed by 2026, instead of 2028, as it now projects.
“My concern is that I don’t think this is aggressive enough. If we want to have an impact in two years, it is one of the programs that requires significant progress.“Camacho said.
The development of the priority plan was ordered by the NEPR after the massive blackout of June 12when nearly 350,000 customers were left without service due to transmission line failures.
At the time of this edition, the AEE was presenting its plans to address hydroelectric plants.