“Impossible” for LUMA Energy to meet new deadline to prepare Integrated Resource Plan

“Impossible” for LUMA Energy to meet new deadline to prepare Integrated Resource Plan

LUMA Energy He stated that the new deadlines that the Puerto Rico Energy Bureau (NEPR) granted –in response to a previous request for an extension– will not be sufficient to complete the review and submit its proposal. Integrated Resource Plan (PIR) of the electrical system, which is why it asked the regulatory body for a “confidential” meeting to explain the current status of the process.

According to LUMA, of the 11 months that have passed since it recruited the firm Black & Veatchat a cost of $3 million, to serve as its technical consultant in developing the PIR, “six have been dedicated to solving software programming problems that caused illogical results” in the scenarios modeled for the future of the power grid.

“The complexity and challenges of Puerto Rico’s electrical system and regulatory requirements, coupled with unforeseen delays associated with modeling software, make the November 29, 2024 delivery deadline impossible to meet.”the consortium stated, referring to the date set by the NEPR in an august resolution.

Kumneger Media
Kumneger Media
Kumneger Media is a News and Entertainment Website & Channel. Kumneger Media in addition to News and Entertainment it is the hub of Politics, Movies, Drama, Music, Comedy, Documentary and More!