He Institute of Puerto Rican Culture (ICP) He requested, this Thursday, the Federal Emergency Management Agency (FEMA) to urgently address reconstruction projects following the partial collapse of the roof of the Conde de Mirasol fort in Vieques yesterday.
“This was a concern that had been shared with FEMA in multiple project progress meetings since the claim was initiated in 2017 and during this year and most recently after the passage of the storm Ernesto.”the ICP denounced in written statements.
“The delay, which we consider excessive, in the processes by the Central Office for Recovery, Reconstruction and Resilience (COR3) and FEMA in the review and approval of the recommendations included by Porticus PSC, the company in charge of expertise and consulting, has caused the necessary works to prevent what happened to be unable to be completed”the entity highlighted.
Fortin Conde de Mirasol, which was built between 1845 and 1855, houses the ICP’s operational offices as well as the Vieques Museum and the Vieques Historical Archives.
Due to the value of its heritage, the structure was included, in 1977, in the National Register of Historic Places and is the last military construction under the Spanish Crown in the Americas.
According to the ICP, after the passage of the Hurricane MariaPorticus PSC concluded that in order to return the Fort to its previous condition, the roof beams had to be repaired and its capacity to withstand these types of atmospheric events improved.
However, the entity pointed out that the delay in the process by COR3 and FEMA resulted in part of the roof of the structure collapsing after the passage of the Tropical Storm Ernesto this past August.
“Although we have had the support of COR3 and FEMA, through required meetings and processes, approvals were not granted to address the property promptly. This is particularly the case at the most critical time, with the processing of the approval of the amendments requested by the ICP and the request for additional mitigation measures to those included by FEMA in the project in order to avoid additional damage to the historic property,” read the organization’s statements.
The ICP reported that, since January 3 of this year, its consultants notified FEMA and COR3 by email of its request for amendment and request for additional funds for mitigation measures for the property.
Following the lack of a response from the federal agency, they submitted, on April 1, in the Grants Portal the request for amendment to the Damage Description and Dimensions (DDD) Report in order to adapt it to the repair method recommended by the expert with the estimated costs and additional elements.
The agency subsequently sent another email to notify that the documents had been submitted, but it was not until May 21 of this year that, according to the ICP, they received a communication from FEMA. In that message, the agency asked that “some details be reviewed and/or clarified, such as removing any mention of termites from any of the documents.”
The ICP indicated that on August 15 it submitted the requested documentation and reported on the damage caused to the fort after Ernesto passed through. After receiving a quote for the mitigation measures and emergency repairs recommended by its consultants, the entity requested, on August 28, emergency funds to cover the expenses.
“During this time, despite being aware of the damage and the urgency to address it, FEMA and COR3 had not issued any other communication or response to the ICP’s request to amend the project and add mitigation measures.”the organization denounced.
“On September 11, 2024, after informing FEMA and COR3 that the roof had finally collapsed in an area of the Fortin and the danger this represents for our employees, COR3 issued the letter expected by FEMA to be able to process our request. Eight months have passed since our communications notifying the risk of inaction and, unfortunately, now what was predicted due to the delay in the processes has occurred.”the entity said.
“We are aware of the commitment of both agencies to the reconstruction process for Puerto Rico and we hope that they can respond to this call to accelerate the processes to jointly implement the action plan, both for Fortin Conde Mirasol in Vieques and for our other historic properties,” the ICP concluded.