Starting this Saturday, Saint Elizabeth, Coamo, Aibonito and Joanna Diaz Finally, they would have greater stability in the electrical service, since LUMA Energy will energize transmission lines 100 and 200, which were out of service since the passage –seven years ago– of the Hurricane Mariathe director of External Affairs of the consortium reported on Friday, Jose Perez.
“Following the work we had begun in June to raise lines 100 and 200, today (Friday) and tomorrow (Saturday), these lines, which had been out of service since 2017, will be energized. Our teams have done a commendable job.“, Perez highlighted, in a public hearing of the Commission for the Development and Oversight of Public Funds of the South Central Region of the House of Representatives.
Describing the work carried out as “major and significant”, Perez dismissed information that had allegedly been “discussed” in the Useras sector, in Santa Isabel, that both lines “would be up in three days”.
“We have conditioned around 84 structures or poles. Of those 84, around 54 are new structures, that is, planted poles that can withstand a capacity of 165 miles of wind. We are mitigating the system and any situation that may occur in the future, and we are using the new pole technology, which helps that segment, about seven miles long, will withstand sustained winds of 165 miles per hour, and It gives the redundancy that has not existed for seven years.“, he added during his participation in the public hearing.
The representative of the people of district 27, Star Martinez Sotochaired the public hearing –the sixth to be held– to follow up on the work carried out on lines 100 and 200, as well as the installation of the transformer that will be moved from Maunabo to Santa Isabel.
“We are pleased that, seven years after Hurricane Maria, the towns in the south have received the good news that lines 100 and 200 have been reestablished to provide a stable system. This work involved the installation of 54 new poles and the repair of another 30, which will help us stabilize the system that has affected our people so much,” said the legislator.
Regarding the transformer that will be installed in the Santa Isabel substation, the cost of the transfer is $370,000The contract has already been signed, and the team should be located in the next few days. LUMA staff stated at the hearing that they must be in office in two weeks.
They also reported that the Federal Emergency Management Agency (FEMA) authorized the purchase of equipment for network automation, which will help reduce response time and the length of time that customers would be without service.
In addition, LUMA managed to purchase 50 new generators – of various voltages – which should be in Puerto Rico before the end of the year to help maintain the stability of the system.