Genera PR: refusal of the federal government to increase temporary generation would delay plant repair for a year

Genera PR: refusal of the federal government to increase temporary generation would delay plant repair for a year

If the federal government does not authorize doubling the amount of temporary generation that it will inject into the electrical grid in Puerto Rico, Genera PR’s projections to bring the generating fleet to an “acceptable” state would be delayed by about a year, estimated this Wednesday the Vice President of Company Operations, Daniel Hernandez Morales.

The effect of that variable It would imply that the objective established by Genera PR of halving the service outages of the generating units would be met by the end of 2025 and not for December 2024.

“To be able to bring it to half (the forced departures) and fulfill it by the end of next year, we need 700 megawatts (MW). If what there is is 350 MW (provided by the Federal Emergency Management Agency, FEMA, in English), I would tell you that, instead of completing the process by 2024, we would be completing it by the end of 2025. We would be taking time, perhaps up to two years,” said Hernandez, in an aside with The new dayafter appearing at a hearing of the Senate Energy Affairs Committee.

During the hearing, chaired by Senator Javier Aponte Dalmau, Hernandez Morales alleged that FEMA chose to cut in half the temporary generation that it would pay for through portable units as a result of a change regarding the guarantee offered, in recent months, by the Electric Power Authority (AEE) regarding the availability of unit #1 of the Aguirre power plant, in Salinas. This unit, which has been out of service for more than a year, has the capacity to produce up to 450 MW, but Hernandez Morales anticipated that it will not be operational until September.

At the moment, FEMA and the United States Army Corps of Engineers (USACE, in English) have only installed and connected to the grid the portable units that operate from the Palo Seco plant in Toa Baja, which since June have produced 150 MW. In mid-September, the megagenerators placed in the San Juan power plant should come into service, which would add 200 MW.

According to the executive, the federal agency plans to keep the units connected until March of next year, although Genera PR seeks to extend that term, at least, until December 2024.

“We have people in dialogue in Washington, and not only Genera, but a coalition of different sectors, who recognize the need to have that additional temporary generation for a longer period of time and bring the condition of the generation fleet to a more acceptable level”said Hernandez Morales, who mentioned that both the governor Pedro Pierluisi and the legislative leadership support the efforts to increase temporary generation and extend the period of permanence of the units.

The maintenance plan that Genera PR expects to execute was reviewed by this newspaper last Sunday, and involves the staggered departures of all the main units of the fleet from now until the end of 2024, with a view to replacing “critical components” that increase their “reliability”. According to Hernandez Morales, based on data that PREPA provided to the company, during the first half of this year, 32% of the generating capacity went out of service monthly, an indicator that the company aims to reduce to between 15% and 16%

“It seems to me that this improvement plan is not executable, according to what we have discussed here. If you do not have those 700 MW of generation available here next month (…), this plan cannot be executed,” Aponte Dalmau stated, to which Hernandez Morales replied that “that is what we have established ”, in reference to the negotiations with the federal authorities.

During the hearing, Senator Aponte Dalmau questioned the projections of the Head of Operations of Genera PR, establishing that the state of the fleet that they have managed since July 1 was “no surprise to anyone.”

Hernandez Morales partially refuted the assertion of the president of the Energy Affairs Commission: he maintained that, in 2021, when he served as director of Generation at PREPA, the rate of forced departures was around 14%.

In response, Aponte Dalmau required Genera PR to deliver to the commission the “inventory” of the state of the plants that the company had at the time of entering the tender that resulted in the operation and maintenance contract.

“We cannot continue here blaming each of the contracting parties for this process,” said the popular legislator.