DNER Secretary attributes to the owners of Sol y Playa that the demolition has not been complied with

DNER Secretary attributes to the owners of Sol y Playa that the demolition has not been complied with

The secretary of the Department of Natural and Environmental Resources (DNER), Anais Rodriguez Vegarejected this Wednesday that the agency had failed to comply with the order of the Court of First Instance in the case against the Sol y Playa condominium, in Rincon, and attributed to the owners that the demolition of the controversial recreational area had not been carried out.

“The agencies concerned have tried to comply with the mandatory itinerary established by the court, on June 20, even with the delays of the defendant in completing the required permits and authorization, apart from other procedures. The reckless, procrastinating, and delinquent conduct exhibited by that party is the real and obvious cause for the fact that, at this time, the order of two years ago has not been complied with.”, indicated Rodriguez Vega in written statements.

On Monday, Judge Miguel Trabal Cuevasof the Aguadilla Court, stated that the owners of the Sol y Playa Condominium had not executed the sentence due to the “failure of government agencies to grant the permits required for the demolition process.”

That was the basis used by the magistrate when accepting the appeal for “habeas corpus” presented by the president of the Council of Owners, Maria Isabel Negron Garciathrough which he requested that an arrest warrant issued against him by the judge be annulled Abid Quinones Portalatin for contempt

After that determination, Negron Garcia – who assumed the direction of the Council of Holders in February – was not admitted to prison.

The owners of Sol y Playa allege, according to the sentence issued by Judge Trabal Cuevas, that the delay in the demolition work arises from the absence of a permit, from the DNER, that grants them access to the land to carry out the works because it is “other people’s property” and in the “public domain” managed by said agency.

Rodriguez Vega confirmed yesterday, Tuesday, to The new day that the owners require a “special authorization” to carry out the work and thus guarantee that the demolition plan submitted “faithfully complies with environmental regulations.”

The permit has not been issued, but not because of the DNER’s delay, but because, according to an information motion submitted by the agency on Monday, Sol y Playa has failed to comply with “regulatory requirements.”

To grant the “special authorization”, everything that the Construction Permit for Demolition (PCOC) contemplates is required, in addition to the payment of a public liability policy, a “performance bond” (performance bond) to guarantee the restoration and a “Protocol for the Management of Endangered Species”, it explains in the document.

Sol y Playa, according to the brief, presented the documents on August 9, but without the corresponding policies or the aforementioned protocol.

“Impossible that by presenting the documentation on August 9, 2023, we do not know the time, and sent to the attention of the Permits Bureau on August 11, it was claimed that, on that same day, the special authorization would be granted. without the corresponding policies and the Protocol for the Management of Endangered Species”, read the motion submitted by the DNER.

The agency also argued that the delay in the work cannot be awarded when the Owners’ Council has said that “they are not financially qualified to carry out the demolition, rubble disposal and restoration works of the impacted area.” “The events during the designated hearing and after cannot be awarded to the DNER”underlined Rodriguez Vega.

During the hearing on Monday before Judge Quinones Portalatin, the legal representative of the Council of Owners, Amy Annette Ruiz Goyco, argued in the courtroom that they had faced problems in hiring an engineer for the work, that the condominium did not have the money to pay for it and that close to 55% of the owners, or 38 of them, had not paid the amount -which amounts to $500,000– to comply with the sentence.

That same day, Ruiz Goyco said that, at that time, there was only one company willing to carry out the work, estimated at $900,000. However, the company “requests 35% of the cost of the work in advance and other requirements.”

The lawyer also confirmed that the PCOC and the Single Incidental Permit (PUI) –which they submitted on July 21– were issued after, on August 10, they complied with the payments of the Insurance Fund Corporation policy of the State and the municipal taxes of construction and patent.

Today, Wednesday, the assistant secretary of the Office of Management and Permits (OGPe), Felix Riveravalidated to this medium that both permits were granted.

The new day He tried to communicate with the lawyer Ruiz Goyco, but it was not possible.

will insist on compliance

For his part, the president of the Planning Board (JP), Julio Lassus Ruizheld that they will insist on their claim to the court for the owners of Sol y Playa to comply with the demolition order.

“We would be requesting compliance with the court order as many times as necessary and the sanctions provided by Law 161 on Permit Reform”, he said in an interview with this medium.

In terms of what would be the legal remedies available, Lassus Ruiz mentioned that this is a matter for the agency’s legal team. “For us, nothing has changed other than that we are going to continue requesting that the order be complied with”, Indian.

The Council of Owners had until March 1 to demolish any construction carried out on the disputed land, after the Court of First Instance declared the construction permit for the recreational area null and void on February 14, 2022, validating the argument of the JP that it was given illegally.