Generate PR objected to the resolution of the Puerto Rico Energy Bureau (NEPR) that orders it to complete the purchase and installation of backup generation units in 2026 – and whose failure to comply would result in the payment of daily fines –, arguing that the agency was quick to conclude that the company had made “false representations” about the cost and time that the acquisition would entail.
The company, which manages the generating fleet of the Electric Power Authority (AEE), called on the NEPR to reverse the order, including warning of fines of up to $25,000 a day for non-complianceand, instead, hold an evidentiary hearing to determine whether, in fact, Genera PR committed the indicated acts.
“If the NEPR does not allow agreements that align with the delivery schedules submitted by the proponents of a competitive process, it is possible that the (purchasing) process will fail”he stressed in a motion submitted on Monday.
According to the company, the NEPR’s September 17 order not only limits its contractual rights as a generation operator, but also “affects the freedom and ownership interests of Genera, to the extent that a finding of false representation impacts its business reputation.”
Likewise, according to the company, the NEPR failed to advise him, in last month’s resolution and order, of his options to request review of the administrative determination.
In summary, the controversy between the company and the regulator revolves around the modifications that Genera PR introduced – with the endorsement of the NEPR – to the process to replace the fleet of so-called “speaker” units, which the generation system needs to respond. to peaks in demand by covering unscheduled departures in the main plants.
Before handing over management to Genera PR, PREPA planned to award, in the summer of 2023, a request for proposals (RFP) for the purchase and installation of the units, with a view to having the machines in operation by the end of 2025. According to PREPA, the RFP would have had an estimated cost of $613 million, 90% covered by federal funds.
Upon entry, in July of last year, Genera PR proposed restarting the procedure under the premise that it would achieve savings, as well as a cut in purchasing time, but this summer it acknowledged that its new schedule envisions the cost rising to $911 million and the installation not being completed until 2027..
According to Genera PR, the increase in costs and the delay in execution is due to elements beyond its control, and it has argued that PREPA would have found it impossible to meet its own projections.
Nevertheless, the NEPR concluded that Genera PR had been negligent in its representations and, in keeping with this, he ordered that, if he does not complete the installation of the units before June 30, 2026, he is exposed to penalties of $25,000 for each day in excess. He also warned him that he would have to finance any costs above PREPA projections that are not covered by the federal government.
“The NEPR has adjudicated controversial facts, many of which arise from estimates and projections that were later affected by exogenous events, without allowing Genera the opportunity to present evidence and have the issues in controversy adjudicated before an examining officer or administrative judge.”pointed out the company, which also alleged that the regulatory body did not define the concept of “misrepresentation,” “what the fundamental elements of the concept are or what evidence satisfied those elements.”
The privatization company stressed, in turn, that it has not failed to comply with the deadlines granted by the NEPR to report the progress of the acquisition process.