If Puerto Rico does not find a way to optimize the reconstruction of its electrical system in the short term, it not only runs the risk that projects financed with federal funds dilate, but would remain tied for a long time to the fossil fuels on which your current depends generating fleet and would face a scenario of “defection” of customers from the core network that would cause dramatic increases in rates within the next five years, the study concluded. Center for a New Economy (CNE) in its most recent publication.
“Part of the problem is precisely that each entity is focusing on a limited area of the problem and there is no agency or entity, right now, that is looking at the interconnection between all of these projects.”. When we talk about the reconstruction or transformation of the system, there are four or five projects that are running simultaneously,” said the director of Public Policy Analysis of the study group, Sergio Marxuachin reference to the repair works of the electrical lines, the transition to the renewable sources and the decision to privatize operations through contracts of LUMA Energy and Generate PRwithout the expected results having been produced so far.
In theory, Marxuach said, the panoramic vision of reconstruction corresponds, at the state level, to the Puerto Rico Energy Bureau (NEPR), and Department of Energy (DOE, in English), at the federal level, but so far none of the agencies has managed to effectively exercise that role.
For a few years now, the CNE has proposed the creation of a “task force”, made up of the federal and state agencies involved in the modernization of the network, which is responsible for harmonizing the different visions and processes that, under the current scheme, They collide and prevent the necessary progress.
“They are running in separate lanes. In theory, that (NEPR and DOE leadership) is supposed to be happening, but you have the NEPR here carrying out some processes, and the DOE there carrying out other processes, and there is not much communication between the twoat least, from what we have seen. In relation to the LUMA and Genera contracts, we have also seen that the Authority for Public-Private Partnerships “It seems to have taken a hands-off attitude,” commented the economist.
According to previous CNE publications, up to 14 state and federal entities intervene in one way or another in the electrical system, from the allocation of funds to the approval of projects and administration of the network.
Marxuach recalled that, in 2012, the administration of Barack Obama created a “task force” to expedite reconstruction work after the devastation caused by the Hurricane Sandy in New York and New Jerseytwo jurisdictions not used to dealing with tropical cyclones.
“This forum was created by executive order, to effectively coordinate the work, what the progress is, where those obstacles are, where the obstacles are and what one agency can do to help another. We have not seen that in Puerto Rico,” he noted, adding that the Central Office of Recovery, Reconstruction and Resilience Nor has it been able to exercise that coordinating role effectively.
Last month, The New Day noted that, within the framework of the electrical reconstruction seven years from Hurricane Maria, only 11.7% of the funds allocated by the federal government had been disbursedwhile it is anticipated that modernization will extend, at least, until 2032. The slow pace of reconstruction was one of the topics addressed in the hearing held, on September 26, by the Subcommittee on Indigenous and Insular Affairs of the federal congress.
chain effect
in the bulletin “Putting together the energy puzzle”published this Thursday, the CNE highlighted the relationship between the short-term stabilization of the transmission and distribution network with the objectives of transforming the generation fleet, a transition that is in its infancy, considering that about 5% of the energy comes from from clean sources, in contrast to the provisional goal of 40% by 2025.
Since the approval of the Integrated Resource Planin 2020, it has not yet been possible to execute any new projects solar energy on a large scale, and the two purchasing “tranches” overseen by the NEPR have fallen short of the established clean generation capacity targets. The NEPR, after a second tranche in which it barely approved contracts that would add 60 megawatts (MW) of solar energy and another 60 MW of battery storage – compared to the goal of 500 MW of energy and 250 MW of storage – alleged that the costs offered by private proponents exceeded appropriate parameters.
This scenario, according to the CNE bulletin, makes it “likely” that dependence on fuels such as natural gas will increase and that, by 2028, “average rates will exceed 35 cents per kilowatt hour”an effect exacerbated by the continued migration of customers to their own energy systems.
“The combination of these factors creates a chain of delays in the transition to 100% renewable generation, followed by failed and costly catch-up efforts, followed by further delays and more spending on failed catch-up efforts,” the company says. publication.
For Marxuach, it is urgent to find alternatives to finance and reduce the costs of clean energy projects on an industrial scale. Last year, the DOE Loan Program Office told The New Day that did not foresee guaranteeing loans to proponents of these projects beyond the first roundbut would correspond to private banking.
The financing problem could, in turn, be reflected in the transmission and distribution network, since it is estimated that there is a gap of nearly $6,000 million between the needs of the system and the allocated funds. Although the DOE anticipated that the Electric Power Authority can access the capital markets by 2028, Marxuach considers that this is an excessively “optimistic” projection, given the delays in financial restructuring.
Given this scenario, the economist recommended listening to the possibilities of receiving funds allocated to electrical cooperatives, which in the United States are grouped under the National Rural Electric Cooperative Association.
“There are entities that are dedicated to developing these projects, which can be structured as cooperatives, which would also have a lower cost of capital”he stressed.