The consortium LUMA Energyin charge of the transmission and distribution system of the country’s electrical network, warned this Thursday that service interruptions could occur due to generation problems.
“There is a high probability of service interruptions due to generation problems,” The company reported in a publication on the X social network, where it urged subscribers to reduce energy consumption between 6:00 and 9:00 pm, the typical period of maximum consumption.
“At LUMA, although we are not responsible for generation, we are in constant communication with the generators (in charge of Genera PR) to minimize the impact on our clients,” added LUMA.
In statements to The New Daythe LUMA spokesperson, Hugo Sorrentiniexplained that The projection “reflects that, at the moment, there will be a generation deficiency in the system.”
“Therefore, as system operators, we have the responsibility to keep loads balanced. “This means that we are inevitably going to have to activate the load relief protocols and some customers may experience interruptions,” he mentioned.
“We will always try to make the relays shorter and with less impact for our clients. However, it depends exclusively on how much generation we have available,” Sorrentini said.
According to data published on the consortium’s generation portal Generate PRat 4:00 pm they had a total generation capacity of 2,785 megawatts (MW), compared to an available capacity of 3,034 MW. In addition, it has a rotating reserve of 256 MW, and an operational reserve of 253 MW.
According to data updated on LUMA’s digital platform, as of 3:45 pm, there were 11,592 (0.79%) customers without electricity service. electrical energy. Of those, 9,150 have temporary service interruptions caused by planned improvement projects.
Currently, the most affected region is Arecibo, with 6,283 clients without service, followed by the Caguas area, with 2,168 and the Mayaguez area, with 1,542. On the other hand, the Ponce region has 1,124 clients without electricity service.
In statements to this medium, the Genera PR spokesperson, Ivan Baezconfirmed that “There are some units that are under repair” and insisted that Puerto Rico needs an additional 565 MW.
“This is a reflection of what we are asking for, both at the local and federal level, that Puerto Rico needs an additional 565 MW as (through) backup units (emergency generators) to be able to face peak hours when there are units under repair or forced outages. ”, he mentioned.
Baez explained that “whenever there are units under repair, there may be limitations in peak hour(s).
Currently, the Genera PR spokesperson specified that units 1 and 2 of the Aguirre plant, in Salinas, are out of service. He announced that unit 1 would come into operation next Monday, while unit 2 could be reactivated by mid-November.
He said that, meanwhile, unit 6 of the San Juan plant would be in service by 2025, as it is undergoing a major repair, and unit 4 of Palo Seco, which broke down last year, would also be operating by the middle of the year. incoming.
On the other hand, this medium learned that the private cogenerator AES You have one unit out of service.