He Puerto Rico Energy Bureau (NEPR) upheld the $8,000 fine it had imposed, in August, on the Electric Power Authority (PREPA) for delaying in delivering a short-term plan for the management of the hydroelectric plants, and ordered the public corporation to show cause why it should not face additional penalties for not having paid since then.
“The NEPR denies PREPA’s August 27 motion requesting reconsideration of the fine imposed. The NEPR has not received evidence, and the administrative file of the case does not show that PREPA has complied with the August 23 order. “The NEPR orders PREPA to pay the aforementioned administrative fine within five days of notification of this resolution and order.”indicates the resolution and order issued on Friday.
The regulatory body then ordered PREPA to show cause why it should not impose additional fines of $5,000 for each day that has elapsed since August 23, when the original one was imposed.
The $8,000 that weighs against PREPA corresponds to a penalty for the 16-day delay in submitting the “priority plan” for the management of hydroelectric plants that the NEPR ordered to formulate after the massive blackouts on June 12. Initially, PREPA argued that it was not its responsibility to submit a plan, since the hydroelectric plants were not part of the failures that were recorded that day, in which up to 350,000 subscribers were left without service simultaneously.
1 / 39 | In the dark: this is how the blackout that left over 340,000 subscribers without electricity is experienced. A first blackout affected the regions of San Juan, Carolina, Bayamon and Caguas on the afternoon of Wednesday, June 12, 2024. Units 5 and 6 of the San Juan plant, along with the emergency generators installed by FEMA, went out of operation. service without notice. – Nahira Montcourt.
LUMA Energy and Generate PR –private operators of the transmission and distribution network and the generating fleet– were also delayed in presenting their priority plans and received fines of $3,500 and $2,500, respectively.. According to the NEPR resolution, Genera PR certified that it had sent the payment on September 11 and LUMA, the following day.
In the case of private administrators, fine payments had to come from the fixed payments they receive for their services, so they could not be claimed as funds reimbursable to PREPA.
The respective priority plans delivered by the three entities in charge of the electrical system compile projects that can be implemented in a two-year window. In recent days, the NEPR held a hearing and has received public comments that, for the most part, criticize components of the plans and the performance of private administrators, pointing out that they do not tend to stabilize and transform the electrical system.