Generate PR you can start using natural gas in three portable generators located at the Palo Seco power plant, in Toa Baja, after the Puerto Rico Energy Bureau (NEPR) approved, with certain conditions, the proposal for the fuel modification, an adjustment that, according to the operator, would result in savings of more than $12 million per year.
In adjudicating Genera PR’s request, the NEPR emphasized that the company left multiple loose ends in its responses to information requests, but that the “balance of interests” favored granting authorization.
“These factors include the urgent need to stabilize fuel prices, reduce energy costs and ensure compliance with the approved Integrated Resource Plan and public energy policy.. Furthermore, the proposal’s potential to improve adherence to environmental requirements and promote the benefits of cleaner fuels supports conditional approval,” NEPR stated in a statement. resolution and order on Friday.
Genera PR’s petition, presented last February, covers three megagenerators – called “MobilePacs” –, each with the capacity to produce up to 27 megawatts (MW), acquired in 2019. To date, the machines have operated on diesel, which will continue to be available as an alternative fuel.
Among the arguments that Genera PR outlined throughout the evaluation process were the benefits that the modification would represent for compliance with federal air quality standards, cost reduction and the possibility of using the units more frequently due to the low in toxic emissions. Specifically, he proposed that machine utilization could be raised to 33% of capacity, even though it has generally remained below 10%.
The NEPR warned, however, that the generators must continue to be used as “peak” units – in the event of increases in demand or forced outages of other units – and not as part of the base fleet..
“Considering the circumstances, the NEPR will closely monitor the situation to ensure that the proposed changes do, in fact, result in significant savings and that the approval does not merely facilitate a fuel modification that modifies a supplier of liquefied natural gas without resulting in tangible benefits.” to consumers,” the NEPR stressed.
Meanwhile, The regulatory body denied the proposal that Genera PR become the owner of the improvements it implemented to make gasification viableby maintaining that it could put future allocations of federal funds or the possibility of other companies using the infrastructure on equal terms.
At the moment, New Fortress Energythe parent company of Genera PR, maintains a natural gas supply contract for eight generation facilities, including Palo Seco.
In resolution and order, The NEPR did not award a similar modification order that Genera PR is pending for the four units of the generation station. Mayaguezwhich have a combined capacity of 220 MW.
“The proposed fuel modification for Mayaguez will be considered in a separate resolution and order to be issued in the near future. Consequently, the determination on the Palo Seco ‘MobilePacs’ does not constitute and will not be considered, constructed or interpreted as a determination on the proposed modification for Mayaguez or for any other facility,” the NEPR stressed.
In the same administrative file, Genera PR also requested in July to switch two units of the Cambalache plant in Arecibo to natural gas, but the NEPR has not yet expressed itself on that proposal.
According to Genera PR, fuel changes can be carried out in six months after receiving authorization.
Resolution and order of the Energy Bureau, dated October 11