A breakdown in one of the switches of a portable unit installed in the area of the Covadonga substation, in San Juan, caused a service interruption that affects about 290 customers, reported this Friday. LUMA Energy.
Hugo Sorrentinispokesperson for the energy consortium, told The New Day that the work to correct the situation could last approximately five hours, while specialized personnel carry out repairs in the area.
According to the spokesperson, the portable unit was located in the area to allow for repair and remodeling work.
The work focuses on the completion of the substation, one of the points where the distribution cables are connected to the installation.
“We understand that it is likely that we will find more things, but we are taking the opportunity to repair everything that is affected to avoid or reduce these customers from going out of service again”said the spokesperson.
Specialized personnel from the San Juan region, including underground and system operations brigades, are on site to address the situation.
Sorrentini indicated that the necessary security measures have already been established so that the brigades can carry out their work.
“We are attending to it at this moment and we hope it will be resolved in the next five hours”he added.
The spokesperson noted that the Covadonga substation remodeling project has been going on for more than a year and responds to the need for continuous maintenance and investment in electrical infrastructure.
According to Sorrentini, last year they worked with the equipment manufacturer, who visited the island and inspected the installation. After that evaluation, it was decided to place the portable unit in the area to keep customers with service while work continues at the substation.