The governor Jennifer Gonzalez Colon announced, this Sunday, the beginning of a comprehensive evaluation of the Superaqueduct, which will take between six to nine months to produce a concrete plan to address the problems that this system faces for the distribution of drinking water for Puerto Rico.
“This evaluation serves a double purpose: to clear up concerns that may be unfounded and, at the same time, establish a plan of corrective and preventive actions that are necessary,” said the engineer. Carlos Pesquera Moralesin a press release sent by La Fortaleza.
Pesquera Morales was the one who recommended the evaluation to the governor, after the recent breakdowns in the system that left thousands of subscribers without service over the weekend, the Executive reported.
According to Pesquera Morales, due to the complexity of the system, the Superaqueduct requires a comprehensive examination of all its components approximately every 25 years.
Among the components that must be evaluated are the main pipeline, joints, valves, river and stream crossings, electromechanical components and the cathodic protection system, a mechanism specifically designed to prevent corrosion.
According to the engineer, this evaluation will produce “a concrete plan of corrective actions with clear priorities, cost estimates and an implementation program” while adding that it is possible that this study will be covered by federal funds from the Federal Emergency Management Agency (FEMA in English).
“We must prioritize the maintenance of our aqueduct system to avoid more vulnerabilities due to lack of review and maintenance for decades,” Gonzalez Colon said in a press release.
Pesquera Morales was appointed, in the summer of last year, special coordinator for the Stabilization of Drinking Water after days of instability in the service in the metropolitan area and some mountain towns. This delivered a 142-page report with a series of strategies in the short term, which include providing better supervision of the work of private contractors that may impact AAA infrastructure and observations to strengthen maintenance logistics, and points out the need to better measure water flows to properly “balance” the distribution network.
Last Wednesday, the Aqueduct and Sewer Authority (AAA) announced that it would be carrying out repairs at the Sergio Cuevas filter plant in Carraizo, but later on Thursday night a breakdown was revealed in the Superaqueduct, which led to the interruption of water service for more than 100,000 subscribers in the metropolitan area of Puerto Rico.
1/12 | Superaqueduct: this is how the megapipeline was built at a cost of $585 million. The idea for the project arose from engineer Antonio Santiago Vazquez, in the 1980s, under the administration of Carlos Romero Barcelo. Then, his idea did not prosper, but it was revived, a decade later, by Pedro Rossello. In the photo, Santiago Vazquez, considered “the father of the Superaqueduct,” stamps his signature on the pipe, when construction was announced in 1996. – TITO GUZMAN
During the repairs of that breakdown, two new breaks arose that exacerbated the crisis for customers of the public corporation, which is currently working to restore service by Monday, June 15.
“Our expectation continues to be to finish by Monday, if there is no further inconvenience”stated engineer Luis Gonzalez Delgado, president of the AAA. “We are already working to be able to access the last fault that we identified today (yesterday Saturday) and basically that is what could add 12 additional hours of work”he explained.
According to Gonzalez Delgado, the failures are concentrated in the joints of the pipe, which is located in a section with an approximate inclination of 30 degrees.
The official estimated that more than 50% of affected customers could have service within the first 24 hours after the system opened, scheduled for Monday.