Three decades after its authorization under the Water Resources Development Actthe Rio Grande de Arecibo flood control project faces an uncertain outlook: the lack of funds to finance a work whose cost could reach $600 million, almost $500 million over original estimates.
The increase responds, mainly, to the redesign that the initiative has required due to the changes in the ground conditions caused by the different atmospheric events that have occurred during the past decades, the senator indicated this Tuesday. Hector “Gaby” Gonzalez Lopezauthor of a resolution to investigate the status of the works.
“It is a project that, for me, as an Arecibo native, is the backbone of the city of Arecibo, because it will help us free up many lands that are currently flooded. The economic development of Arecibo also depends on much of these lands”said.
In a meeting called today by Gonzalez Lopez, they participated Jose D. Bilbao, Alberto Gonzalez, Walter Rodriguez and Luis A. Ruizof the United States Army Corps of Engineers; officials of the Department of Natural and Environmental Resources (DRNA); the mayor of Arecibo, Carlos Ramirez Irizarry; and the municipal administrator Luis Rodriguez.
Currently, according to information provided by the Corps of Engineers, the project has an allocation of $82 million, money that is being used for the redesign. “It could be that, when they finish the design stage, we could be talking about $50 million left,” Gonzalez Lopez said.
The legislator explained that the Corps of Engineers promised to deliver a final projection of the cost of the project, although he announced that the preliminary figure is already around $600 million. A clear budget outlook, the Senate indicated, will allow them to define the strategy to lobby for funds in the Congresstogether with the resident commissioner, Pablo Jose Hernandezand the governor Jennifer Gonzalez.
Despite the enormous challenge that identifying the funds represents, both Gonzalez Lopez and Ramirez Irizarry insisted on the urgency of the project.
“It is a vital project for our people and for those who think about investing in Puerto Rico. This project will free up hundreds of acres of land that can be used for commercial, residential and agricultural use.”, the mayor pointed out.
“In addition, we save lives because deaths have already been recorded in those flood-prone areas”he added, also highlighting that the project would help raise the value of properties in the area.
Currently, explained the first municipal executive, they are affected by the floods the communities of La Puntilla, Reparto Martell, Rodriguez Olmos, Victor Rojas, Buenos Aires, the urban area and PR-2, among others.
The recommended plan combines retaining walls and dikes along the Arecibo River, channel improvements, replacement of three bridges, a diversion canal on the Santiago River, a dike and short channel on the Tanama River, a wetland mitigation site, and recreational facilities.
At the moment, only the “Contract 1” phase has been completed, which included the construction of the dam and improvements to the Tanama River canal, the PR-22 dam and the Santiago River diversion canal. This initial phase was completed and handed over to the DRNA for operation and maintenance in 2011.