Some 188,000 subscribers that serve the Sergio Cuevas filter plant still do not have drinking water service, after one of the seven jobs scheduled by the Aqueduct and Sewer Authority (AAA) will not finish in the scheduled time.
The executive president of the AAA, Luis Gonzalez Delgadoreported in a radio interview with WKAQ-580 that the plant remains out of operation because The repair of an outlet pipe has not yet been completed, specifically a leak that, he indicated, had been in the facility for years.
“The reality of the case is that everything in the Sergio Cuevas service area is still without water service”said the official, noting that the revised expectation is that the work can be completed in the morning hours of Wednesday.
Once the repair is completed, the public corporation hopes to begin operating the plant so that the affected communities begin to recover drinking water service as the day progresses and the facility reaches its operational level again.
1 / 13 | The water crisis does not let up: residents of Rio Grande face 48-hour rationing. Rio Grande is one of several municipalities that has been affected by rationing amid the water crisis and drought. – Ramon “Tonito” Zayas
The service area of the Sergio Cuevas plant includes sectors of Carolina, San Juan, Trujillo Alto, as well as parts of Canovanas, Juncos and Gurabo, among other municipalities.
Gonzalez Delgado indicated that the other scheduled works, including work on the Carraizo dam and network-level projects, such as the installation of valves in several distribution pipelines, were completed on time. However, he maintained that the pending repair in Sergio Cuevas was more complex than anticipated.
“The only thing missing is the repair of this leak. The work was much more complex than I expected”recognized the president of the AAA, explaining that, unlike repairs carried out outside a plant, in this case the work is carried out in a confined space.
“The complexity of the pipeline at that point caused what we are now announcing and reporting. But we are going to continue working”assured the engineer.
The official assured that the plant is ready to receive the water supply from Carraizo and begin operations as soon as the repair of the leak is completed.
According to Gonzalez Delgado, Once the plant comes into operation, the sectors served by gravity, particularly areas of Carolina and Rio Piedras, could begin to see service during the first 24 hours. However, he clarified that the plant is not yet operating, so customers continue without service.
Likewise, he explained that people who report water at low pressures could be receiving remnants of reserves in the pipes, but warned that this condition would be temporary until the plant’s operation is formally restarted.